Type in search terms.
MASTER TABLE OF CONTENTS
Webequie Supply Road Project
May 1, 2025
AtkinsRéalis Ref: 661910
Draft Environmental Assessment Report / Impact Statement
MASTER TABLE OF CONTENTS
Contents
1. Introduction……………………………………………………………………………………………………………………… 1-3
- Project Overview……………………………………………………………………………………………………… 1-3
- Project Location………………………………………………………………………………………… 1-4
- Project Proponent……………………………………………………………………………………………………. 1-7
- Proponent Contact Information…………………………………………………………………….. 1-7
- Overview of Webequie First Nation……………………………………………………………….. 1-8
- Webequie Project Team and Elders’ Guiding Principles……………………………………… 1-9
- Project Team……………………………………………………………………………………………. 1-9
- Proposed or Anticipated Financial Support………………………………………………………. 1-9
- Background and Purpose of the Project………………………………………………………………………. 1-10
- Background and Context…………………………………………………………………………… 1-10
- Purpose and Rationale for the Project…………………………………………………………… 1-12
- Rationale for Project…………………………………………………………………. 1-13
- Legislative and Regulatory Framework………………………………………………………………………… 1-16
- Ontario Environmental Assessment Act………………………………………………………… 1-16
- Canada Impact Assessment Act………………………………………………………………….. 1-17
- Regional Assessment of Ring of Fire Area…………………………………….. 1-18
- Process for Federal-Provincial Coordination…………………………………………………… 1-19
- Other Relevant Federal Permits and Approvals………………………………………………. 1-20
- Other Relevant Provincial Permits and Approvals……………………………………………. 1-21
- Report Organization and Presentation…………………………………………………………………………. 1-24
- References…………………………………………………………………………………………………………… 1-25
2. Engagement and Consultation Summary……………………………………………………………………………… 2-4
- Overview of Engagement and Consultation Program……………………………………………………….. 2-4
- Regulatory Engagement and Consultation…………………………………………………………………….. 2-5
- Engagement and Consultation Prior to Initiation of the EA/IS Phase……………………… 2-5
- Provincial and Federal Regulatory Requirements……………………………………………… 2-6
- Fulfillment of Duty to Consult……………………………………………………….. 2-7
- Issues Resolution………………………………………………………………………. 2-7
- Identification of Participants……………………………………………………………………………………….. 2-8
- Indigenous Communities and Groups…………………………………………………………….. 2-8
- Stakeholder Participants……………………………………………………………………………. 2-10
- Ontario Government Review Team and Federal Agencies………………… 2-10
- Engagement Milestones and Timelines…………………………………………………………. 2-11
- Indigenous Communities/Groups Engagement and Consultation……………………………………….. 2-12
- Principles and Approach to Engagement and Consultation………………………………… 2-12
- Webequie-Led Indigenous Engagement and Consultation…………………. 2-12
- Principles and Approach to Engagement and Consultation………………………………… 2-12
- Regulatory Engagement and Consultation…………………………………………………………………….. 2-5
- Elders’ Guiding Principles………………………………………………………….. 2-13
- Webequie First Nation Three-Tier Approach…………………………………… 2-13
- How Indigenous Knowledge was Obtained, Used and Protected…………………………. 2-15
- Indigenous Engagement and Consultation Methods………………………………………… 2-17
- Newsletters…………………………………………………………………………….. 2-21
- Summary of Indigenous Engagement and Consultation Activities……………………….. 2-26
- Round 1 – Engagement and Consultation Activities…………………………. 2-26
- Round 2 – Engagement and Consultation Activities…………………………. 2-29
- Round 3 – Engagement and Consultation Activities…………………………. 2-34
- Summary of Issues and Concerns Raised by Indigenous Communities and
Groups and Status of Resolution…………………………………………………………………. 2-39
- Public and Stakeholder Engagement and Consultation Methods……………………………………….. 2-53
- Summary of Engagement and Consultation Activities for the Public and
Stakeholders…………………………………………………………………………………………… 2-54
- Project Notifications and Monthly Newsletters………………………………… 2-54
- Notices to Stakeholders…………………………………………….. 2-54
- Monthly Newsletter………………………………………………….. 2-55
- Public Information Centres…………………………………………………………. 2-55
- Project Website……………………………………………………………………….. 2-56
- Provincial and Federal Agencies Review of Study Plans and
- Notices to Stakeholders…………………………………………….. 2-54
Baseline Studies……………………………………………………………………… 2-56
- Feedback for Evaluation of Alternatives………………………… 2-57
- Summary of Issues and Concerns Raised by the Public and Stakeholders and
Status of Resolution…………………………………………………………………………………. 2-58
- Record of Engagement and Consultation……………………………………………………………………… 2-70
- Ongoing and Proposed Future Engagement and Consultation………………………………………….. 2-71
- References…………………………………………………………………………………………………………… 2-72
3 Evaluation of Project Alternatives……………………………………………………………………………………….. 3-4
- Alternatives to the Undertaking……………………………………………………………………………………. 3-5
- Method for Evaluating Alternatives to the Undertaking……………………………………….. 3-6
- Evaluation of Alternatives to the Undertaking…………………………………………………… 3-7
- Alternative 1: Do Nothing – Null Alternative……………………………………… 3-7
- Alternative 2: Upgrade Existing Trail System to Seasonal Winter Road….. 3-7
- Alternative 3: Alternative Modes of Transportation…………………………….. 3-8
- Alternative 4: Manage Transportation Demand……………………………….. 3-12
- Alternative 5: New All-Season Road…………………………………………….. 3-12
- Preferred “Alternative to the Undertaking”……………………………………………………… 3-12
- Identification of “Alternative Methods of Carrying Out the Undertaking”………………………………. 3-13
- Background Studies………………………………………………………………………………… 3-14
- Alternate Corridors – Screening Level Assessment…………………………………………. 3-16
- Identification of Alternate Concept-Level Corridors………………………….. 3-16
- Conclusion and Rationale for Selection of the Preferred Corridor – Screening Level Assessment…………………………………………………………………………………… 3-33
- Alternate Routes Identified for Assessment…………………………………………………… 3-33
- Alternative 1…………………………………………………………………………… 3-36
- Alternative 2…………………………………………………………………………… 3-36
- Alternative 3…………………………………………………………………………… 3-37
- Method for Selection of Preferred Route Within the Preferred Corridor………………… 3-41
- Data Collection………………………………………………………………………. 3-42
- Select and Weight the Factors, Disciplines, and Criteria…………………… 3-42
- Select and Score Indicators………………………………………………………. 3-43
- Build and Validate Baseline Model………………………………………………. 3-46
- Run the Model and Standardize Scores……………………………………….. 3-46
- Review Results and Select Preferred Route………………………………….. 3-48
- Sensitivity Analyses……………………………………………………………………………………………….. 3-52
- Project Supportive Infrastructure Alternatives……………………………………………………………….. 3-57
- Alternate Aggregate Sources – Screening Level Assessment……………………………. 3-57
- Alternate Aggregate Sources…………………………………………………….. 3-57
- Screening of Alternate Aggregate Sources……………………………………. 3-58
- Aggregate Source Locations and Access Roads……………………………………………. 3-63
- Construction Camps………………………………………………………………………………… 3-68
- Alternate Aggregate Sources – Screening Level Assessment……………………………. 3-57
- References…………………………………………………………………………………………………………… 3-71
4. Project Description…………………………………………………………………………………………………………… 4-5
- Project Overview and Location…………………………………………………………………………………… 4-5
- Project Design and Planning………………………………………………………………………………………. 4-5
- Road Design and Applicable Design Criteria and Standards……………………………….. 4-5
- Environmental Planning……………………………………………………………………………… 4-7
- Project Components………………………………………………………………………………………………… 4-7
- Roadway………………………………………………………………………………………………… 4-8
- Road Geometric Design…………………………………………………………….. 4-8
- Horizontal Alignment…………………………………………………. 4-8
- Vertical Alignment…………………………………………………….. 4-9
- Road Cross-Section and Cross-Fall………………………………………………. 4-9
- Road Foundation and Driving Surface………………………………………….. 4-10
- Road Design in Peatlands…………………………………………. 4-11
- Road Geometric Design…………………………………………………………….. 4-8
- Roadway………………………………………………………………………………………………… 4-8
- Project Design and Planning………………………………………………………………………………………. 4-5
- Roadside Safety…………………………………………………………………….. 4-13
- Maintenance Turnaround Areas and Maintenance/Rest Areas…………… 4-13
- Illumination…………………………………………………………………………….. 4-15
- Intersections………………………………………………………………………….. 4-15
- Fencing and Signage……………………………………………………………….. 4-15
- Drainage and Stormwater Management……………………………………………………….. 4-15
- Roadside Ditches……………………………………………………………………. 4-16
- Waterbody Crossings – Bridges and Culverts………………………………… 4-16
- Structure Foundations……………………………………………… 4-21
- Structural Considerations and Enhanced Drainage Design Standards for Water Crossings………………………………….. 4-22
- Temporary and Permanent Supporting Infrastructure………………………………………. 4-24
- Aggregate/Rock Source Areas (Pits and Quarries)………………………….. 4-24
- Aggregate Source Area ARA-2…………………………………… 4-25
- Aggregate Source Area – ARA-4…………………………………. 4-28
- Access Roads………………………………………………………………………… 4-31
- Construction Camps with Laydown/Storage Areas………………………….. 4-32
- Power Supply and Communications…………………………………………….. 4-34
- Maintenance and Storage Facility……………………………………………….. 4-34
- Storage of Fuels, Explosives and Wastes…………………………………….. 4-35
- Aggregate/Rock Source Areas (Pits and Quarries)………………………….. 4-24
- Project Phases and Activities…………………………………………………………………………………… 4-36
- Project Phases and Schedule…………………………………………………………………….. 4-36
- Construction Phase Activities…………………………………………………………………….. 4-37
- Surveying and Staking……………………………………………………………… 4-38
- Vegetation Clearing and Grubbing………………………………………………. 4-38
- Construction and Use of Supportive Infrastructure………………………….. 4-38
- Temporary Construction Camps with Laydown/Storage Areas4-39
- Temporary Access Roads and Waterbody Crossings………. 4-40
- Aggregate Extraction and Processing Activities at Pits/Quarries4-41
- Maintenance and Storage Facility……………………………….. 4-43
- Construction of Proposed Road…………………………………………………. 4-43
- Permanent Waterbody Crossing Structures…………………………………… 4-45
- Decommissioning and Site Restoration/Reclamation……………………….. 4-46
- Materials and Equipment Delivery……………………………………………….. 4-47
- Potential Emissions, Discharges, and Wastes……………………………….. 4-63
- Environmental Monitoring…………………………………………………………. 4-64
- Environmental Protection and Controls………………………………………… 4-64
- Operations Phase……………………………………………………………………………………. 4-65
- Maintenance and Operation Activities………………………………………….. 4-66
- Visual Patrols and Inspections of Road………………………… 4-66
- Vegetation Management…………………………………………… 4-66
- Repair and Rehabilitation of Culverts and Bridges………….. 4-67
- Resurfacing and Repair to Road Surface and Shoulders….. 4-67
- Aggregate Extraction and Processing………………………….. 4-68
- Dust Control…………………………………………………………… 4-69
- Road Drainage System Maintenance…………………………… 4-69
- Access Road Maintenance………………………………………… 4-69
- Maintenance and Storage Facility……………………………….. 4-70
- Winter Maintenance…………………………………………………. 4-70
- Spills and Emergency Response………………………………… 4-71
- Potential Emissions, Discharges, and Wastes……………….. 4-71
- Equipment Requirements………………………………………………………….. 4-72
- Environmental Monitoring…………………………………………………………. 4-73
- Environmental Protection and Controls………………………………………… 4-73
- Project Workforce Requirements……………………………………………………………………………….. 4-74
- Construction Workforce……………………………………………………………………………. 4-74
- Operations Workforce……………………………………………………………………………… 4-82
- Training…………………………………………………………………………………………………. 4-83
- Management Plans………………………………………………………………………………………………… 4-84
- Construction Environmental Management Plan Framework……………………………….. 4-84
- Content of the CEMP……………………………………………………………….. 4-85
- Contents of Component Management Plans………………………………….. 4-85
- Operation Environmental Management Plan Framework…………………………………… 4-86
- Construction Environmental Management Plan Framework……………………………….. 4-84
- Summary of Project Changes…………………………………………………………………………………… 4-86
- References…………………………………………………………………………………………………………… 4-86
- Vegetation Management…………………………………………… 4-66
5. Environmental Assessment / Impact Assessment Approach and Methods………………………………… 5-4
- Identification of Valued Components……………………………………………………………………………. 5-5
- Assessment of Effects on Valued Components………………………………………………………………. 5-6
- Scope of the Assessment…………………………………………………………………………… 5-8
- Regulatory and Policy Setting……………………………………………………… 5-8
- Consideration of Input from Engagement and Consultation Activities……. 5-8
- Incorporation of Indigenous Knowledge and Land and Resource Use Information……………………………………………………………………………… 5-8
- Spatial and Temporal Boundaries……………………………………………….. 5-10
- Spatial Boundaries………………………………………………….. 5-11
- Temporal Boundaries………………………………………………. 5-11
- Identification of Project Interactions with VCs…………………………………. 5-11
- Scope of the Assessment…………………………………………………………………………… 5-8
- Assessment of Effects on Valued Components………………………………………………………………. 5-6
- Existing Conditions…………………………………………………………………………………… 5-13
- Gender Based Analysis Plus (GBA+) Approach………………………………. 5-14
- Identification of Potential Effects, Pathways and Indicators………………………………… 5-14
- Gender Based Analysis Plus (GBA+) Approach………………………………. 5-15
- Mitigation and Enhancement Measures………………………………………………………… 5-16
- Gender Based Analysis Plus (GBA+) Approach………………………………. 5-17
- Characterization of Net Effects……………………………………………………………………. 5-17
- Determination of Significance……………………………………………………………………… 5-19
- Assessment of Cumulative Effects……………………………………………………………….. 5-20
- Prediction Confidence in the Assessment………………………………………………………. 5-21
- Follow-up and Compliance Monitoring Programs…………………………………………….. 5-22
- Assessment of Other Effects…………………………………………………………………………………….. 5-23
- Assessment of Accidents and Malfunctions……………………………………………………. 5-23
- Effects of the Environment on the Project………………………………………………………. 5-23
- Effects of the Project in the Context of Canada’s Environmental Obligations………….. 5-24
- Project’s Contribution to Sustainability………………………………………………………….. 5-24
- Summary of the Assessment…………………………………………………………………………………….. 5-25
- Evaluate the Advantages and Disadvantages…………………………………………………. 5-26
- References…………………………………………………………………………………………………………… 5-26
6 Assessment of Effects on Geology, Terrain, and Soils…………………………………………………………… 6-5
- Scope of the Assessment………………………………………………………………………………………….. 6-5
- Regulatory and Policy Setting………………………………………………………………………. 6-5
- Consideration of Input from Engagement and Consultation Activities…………………….. 6-9
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…… 6-13
- Valued Component and Indicators……………………………………………………………….. 6-16
- Spatial and Temporal Boundaries………………………………………………………………… 6-17
- Spatial Boundaries…………………………………………………………………… 6-17
- Temporal Boundaries……………………………………………………………….. 6-19
- Identification of Project Interactions with Geology, Terrain, and Soils…………………… 6-19
- Existing Conditions…………………………………………………………………………………………………. 6-21
- Methods………………………………………………………………………………………………… 6-22
- Desktop Review of Background Information…………………………………… 6-22
- Field Surveys………………………………………………………………………….. 6-22
- Results………………………………………………………………………………………………….. 6-23
- Regional Geology……………………………………………………………………. 6-23
- Tectonic Setting………………………………………………………. 6-23
- Structural Geology…………………………………………………… 6-23
- Lithology……………………………………………………………….. 6-25
- Regional Geology……………………………………………………………………. 6-23
- Methods………………………………………………………………………………………………… 6-22
- Local Geology…………………………………………………………………………. 6-25
- Quaternary Geology…………………………………………………. 6-25
- Geochemical Analysis………………………………………………………………. 6-27
- Geologic Hazards……………………………………………………………………. 6-29
- Ecoregions…………………………………………………………………………….. 6-31
- Terrain………………………………………………………………………………….. 6-31
- Soils……………………………………………………………………………………… 6-40
- Identification of Potential Effects, Pathways and Indicators………………………………………………. 6-49
- Change to Geology and Geochemistry………………………………………………………….. 6-49
- Alteration of Topography and Terrain……………………………………………………………. 6-50
- Change to Soil Quality………………………………………………………………………………. 6-50
- Loss of Soil Resources……………………………………………………………………………… 6-50
- Mitigation Measures………………………………………………………………………………………………… 6-53
- Management Plans………………………………………………………………………………….. 6-53
- Mitigation Measures…………………………………………………………………………………. 6-54
- Characterization of Net Effects………………………………………………………………………………….. 6-61
- Potential Effect Pathways Not Carried Through for Further Assessment……………….. 6-62
- Predicted Net Effects………………………………………………………………………………… 6-63
- Change to Geology and Geochemistry………………………………………….. 6-63
- Alteration of Topography and Terrain……………………………………………. 6-64
- Change to Soil Quality………………………………………………………………. 6-64
- Loss of Soil Resources……………………………………………………………… 6-65
- Summary………………………………………………………………………………………………. 6-65
- Determination of Significance……………………………………………………………………………………. 6-67
- Cumulative Effects………………………………………………………………………………………………….. 6-70
- Prediction Confidence in the Assessment…………………………………………………………………….. 6-70
- Predicted Future Condition of the Environment if the Project Does Not Proceed……………………. 6-71
- Follow-Up and Monitoring…………………………………………………………………………………………. 6-71
- References…………………………………………………………………………………………………………… 6-72
7. Assessment of Effects on Surface Water Resources……………………………………………………………… 7-5
- Scope of the Assessment………………………………………………………………………………………….. 7-5
- Regulatory and Policy Setting………………………………………………………………………. 7-5
- Consideration of Input from Engagement and Consultation Activities…………………….. 7-9
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…… 7-17
- Valued Component and Indicators……………………………………………………………….. 7-21
- Spatial and Temporal Boundaries………………………………………………………………… 7-23
- Spatial Boundaries…………………………………………………………………… 7-23
- Temporal Boundaries……………………………………………………………….. 7-23
- Identification of Project Interactions with Surface Water Resources……………………… 7-25
- Existing Conditions…………………………………………………………………………………………………. 7-27
- Methods………………………………………………………………………………………………… 7-27
- Desktop Review of Background Information…………………………………… 7-29
- Surface Water Quantity…………………………………………………………….. 7-29
- Peak Discharge………………………………………………………. 7-29
- Waterbody Crossing Hydraulics and High-Water Level…….. 7-31
- Surface Water Quality………………………………………………………………. 7-31
- Sampling Locations………………………………………………….. 7-31
- Sampling Parameters……………………………………………….. 7-32
- Sediment Quality……………………………………………………………………… 7-33
- Sampling Locations………………………………………………….. 7-33
- Sampling Parameters……………………………………………….. 7-33
- Results………………………………………………………………………………………………….. 7-34
- Surface Water Quantity…………………………………………………………….. 7-34
- Peak Discharge………………………………………………………. 7-34
- Waterbody Crossing Hydraulics and High-Water Level…….. 7-35
- Surface Water Quality………………………………………………………………. 7-35
- Sediment Quality……………………………………………………………………… 7-44
- Surface Water Quantity…………………………………………………………….. 7-34
- Methods………………………………………………………………………………………………… 7-27
- Identification of Potential Effects, Pathways, and Indicators……………………………………………… 7-44
- Change in Surface Water Quantity………………………………………………………………. 7-45
- Change in Surface Water Quality………………………………………………………………… 7-46
- Change in Sediment Quality……………………………………………………………………….. 7-47
- Mitigation Measures………………………………………………………………………………………………… 7-51
- Dewatering, Water Takings, and Discharges………………………………………………….. 7-51
- Vegetation Clearing and Grubbing……………………………………………………………….. 7-52
- Installation of Culverts and Bridges………………………………………………………………. 7-52
- Permanent Waterbody Crossings………………………………………………………………… 7-53
- Roadway Drainage Design………………………………………………………………………… 7-53
- Accidental Spills and Leaks………………………………………………………………………… 7-53
- Blasting of Rock………………………………………………………………………………………. 7-54
- Construction and Maintenance Activities……………………………………………………….. 7-54
- Disposal of Waste……………………………………………………………………………………. 7-54
- Summary………………………………………………………………………………………………. 7-55
- Characterization of Net Effects………………………………………………………………………………….. 7-67
- Potential Effect Pathways Not Carried Through for Further Assessment……………….. 7-69
- Predicted Net Effects………………………………………………………………………………… 7-69
- Change in Surface Water Quantity………………………………………………. 7-70
- Short-term water takings…………………………………………… 7-70
- Short-term discharges of construction water, wastewater, or wash water…………………………………………………………. 7-70
- Land cover changes resulting in changes to infiltration and runoff rates and volumes…………………………………….. 7-70
- Installation of waterbody crossing structures leading to temporary changes to discharge rates upstream or
- Short-term water takings…………………………………………… 7-70
downstream of waterbody crossings……………………………. 7-71
- Permanent waterbody crossings leading to changes in local hydraulics (flow depth/water level and velocity)………. 7-71
- Road maintenance resulting in changes to overland runoff drainage patterns……………………………………………………. 7-71
- Change in Surface Water Quality………………………………………………… 7-72
- Short-term discharges of construction water, wastewater,
or wash water…………………………………………………………. 7-72
- Blasting activities releasing chemical constituents into nearby waterbodies…………………………………………………. 7-72
- Road maintenance activities leading to the deposition of sediment into waterbodies………………………………………… 7-72
- Change in Sediment Quality………………………………………………………. 7-73
- Short-term discharges of construction water, wastewater,
or wash water runoff………………………………………………… 7-73
- Blasting activities releasing chemical constituents into nearby waterbodies…………………………………………………. 7-73
- Road maintenance activities leading to the deposition of sediment into waterbodies………………………………………… 7-73
- Summary………………………………………………………………………………………………. 7-73
- Determination of Significance…………………………………………………………………………………… 7-77
- Surface Water Quantity…………………………………………………………………………….. 7-78
- Surface Water Quality………………………………………………………………………………. 7-78
- Sediment Quality…………………………………………………………………………………….. 7-78
- Cumulative Effects………………………………………………………………………………………………… 7-78
- Prediction Confidence in the Assessment……………………………………………………………………. 7-79
- Predicted Future Condition of the Environment if the Project Does Not Proceed…………………… 7-80
- Follow-Up and Monitoring………………………………………………………………………………………… 7-80
- References…………………………………………………………………………………………………………… 7-81
8 Assessment of Effects on Groundwater Resources……………………………………………………………….. 8-5
- Scope of the Assessment………………………………………………………………………………………….. 8-5
- Regulatory and Policy Setting………………………………………………………………………. 8-5
- Consideration of Input from Engagement and Consultation Activities…………………….. 8-8
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…… 8-12
- Valued Component and Indicators……………………………………………………………….. 8-16
- Spatial and Temporal Boundaries………………………………………………………………… 8-16
- Spatial Boundaries…………………………………………………………………… 8-16
- Temporal Boundaries……………………………………………………………….. 8-17
- Identification of Project Interactions with Groundwater Resources……………………….. 8-19
- Existing Conditions…………………………………………………………………………………………………. 8-21
- Methods………………………………………………………………………………………………… 8-21
- Documents Reviewed During the Desktop Study…………………………….. 8-21
- Summary of Field Work Programs……………………………………………….. 8-22
- Results………………………………………………………………………………………………….. 8-23
- Geological and Hydrogeological Settings………………………………………. 8-23
- Groundwater Quantity………………………………………………………………. 8-23
- Groundwater Quality………………………………………………………………… 8-24
- Methods………………………………………………………………………………………………… 8-21
- Identification of Potential Effects, Pathways, and Indicators……………………………………………… 8-24
- Vegetation Clearing and Grubbing……………………………………………………………….. 8-25
- Site Grading / Ground Hardening………………………………………………………………… 8-26
- Water Balance Analysis – Methodology………………………………………… 8-26
- Water Balance Analysis – Results……………………………………………….. 8-28
- Blasting of Rocks…………………………………………………………………………………….. 8-31
- Extraction, Cut, Excavation, Stockpiling and Backfilling…………………………………….. 8-32
- Dewatering / Pumping………………………………………………………………………………. 8-34
- Dewatering for Structure Foundations…………………………………………… 8-35
- Dewatering at Aggregate Sites……………………………………………………. 8-36
- Water Supply Wells………………………………………………………………….. 8-41
- Road Construction……………………………………………………………………………………. 8-42
- Disposal of Wastes………………………………………………………………………………….. 8-43
- Summary………………………………………………………………………………………………. 8-43
- Mitigation Measures………………………………………………………………………………………………… 8-45
- Vegetation Clearing and Grubbing……………………………………………………………….. 8-45
- Site Grading/Ground Hardening………………………………………………………………….. 8-46
- Blasting of Rock………………………………………………………………………………………. 8-46
- Extraction, Cut, Excavation, Stockpiling and Backfilling…………………………………….. 8-46
- Dewatering / Pumping………………………………………………………………………………. 8-47
- Road Construction…………………………………………………………………………………… 8-48
- Disposal of Wastes…………………………………………………………………………………. 8-48
- Summary………………………………………………………………………………………………. 8-49
- Characterization of Net Effects…………………………………………………………………………………. 8-53
- Potential Effect Pathways Not Carried Through for Further Assessment………………. 8-54
- Predicted Net Effects………………………………………………………………………………. 8-54
- Change in Groundwater Quantity………………………………………………… 8-55
- Increase of Groundwater Levels due to Vegetation Clearing and Grubbing……………………………………………… 8-55
- Reduction in Recharge and Lowering of Groundwater Levels due to Site Grading/Ground Hardening……………….. 8-55
- Alteration of Groundwater Flow Directions and Pathways and Lowering of Groundwater Levels due to Blasting of Rocks…………………………………………………………………… 8-56
- Alteration of Groundwater Flow Directions and Pathways and Lowering of Groundwater Levels due to Extraction, Cut, Excavation, and Backfilling…………………………………. 8-56
- Lowering of Groundwater Levels due to Dewatering/Pumping8-56
- Alteration of Groundwater Level and Flow Direction due to Road Construction………………………………………………….. 8-57
- Change in Groundwater Quality………………………………………………….. 8-57
- Alteration of Groundwater Quality due to Blasting of Rocks .8-57
- Change in Groundwater Quantity………………………………………………… 8-55
- Summary………………………………………………………………………………………………. 8-57
- Determination of Significance…………………………………………………………………………………… 8-60
- Cumulative Effects………………………………………………………………………………………………… 8-63
- Prediction Confidence in the Assessment……………………………………………………………………. 8-63
- Predicted Future Condition of the Environment if the Project Does Not Proceed…………………… 8-64
- Follow-Up and Monitoring………………………………………………………………………………………… 8-64
- References…………………………………………………………………………………………………………… 8-65
9 Assessment of Effects on Atmospheric Environment…………………………………………………………….. 9-7
- Scope of the Assessment…………………………………………………………………………………………. 9-7
- Regulatory and Policy Setting……………………………………………………………………… 9-7
- Consideration of Input from Engagement and Consultation Activities………………….. 9-13
- Incorporation of Indigenous Knowledge and Land and Resource Use Information….. 9-24
- Valued Component and Indicators………………………………………………………………. 9-29
- Air Quality Basics……………………………………………………………………. 9-29
- Air Contaminants of Interest………………………………………. 9-29
- Relevant Air Quality Criteria and Standards…………………… 9-29
- Air Quality Basics……………………………………………………………………. 9-29
- Greenhouse Gas Emissions Basics…………………………………………….. 9-31
- Greenhouse Gases of Interest……………………………………. 9-31
- Emission Factors Considered in the GHG Emissions Assessment…………………………………………………………… 9-31
- Noise and Vibration Basics……………………………………………………….. 9-32
- Noise……………………………………………………………………. 9-32
- Vibration……………………………………………………………….. 9-36
- Lighting Basics……………………………………………………………………….. 9-36
- Indicators………………………………………………………………………………. 9-36
- Spatial and Temporal Boundaries……………………………………………………………….. 9-38
- Spatial Boundaries………………………………………………………………….. 9-38
- Temporal Boundaries………………………………………………………………. 9-39
- Identification of Project Interactions with Atmospheric Environment…………………….. 9-43
- Existing Conditions………………………………………………………………………………………………… 9-45
- Methods……………………………………………………………………………………………….. 9-46
- Air Quality……………………………………………………………………………… 9-46
- Greenhouse Gases (GHGs)………………………………………………………. 9-49
- Noise and Vibration…………………………………………………………………. 9-49
- Measurements of Background Ambient Sound Levels…….. 9-49
- Identification of Noise Sensitive Areas…………………………. 9-51
- Background Sound Levels………………………………………… 9-51
- Vibration……………………………………………………………………………….. 9-52
- Lighting………………………………………………………………………………… 9-52
- Results…………………………………………………………………………………………………. 9-52
- Air Quality……………………………………………………………………………… 9-52
- Greenhouse Gases (GHGs)………………………………………………………. 9-56
- Noise……………………………………………………………………………………. 9-59
- Noise Monitoring Results………………………………………….. 9-59
- Identification of Noise Sensitive Areas…………………………. 9-60
- Summary of Background Sound Levels Adopted for the Assessment…………………………………………………………… 9-60
- Vibration……………………………………………………………………………….. 9-61
- Lighting………………………………………………………………………………… 9-61
- Methods……………………………………………………………………………………………….. 9-46
- Identification of Potential Effects, Pathways and Indicators……………………………………………… 9-62
- Change in Air Quality……………………………………………………………………………….. 9-62
- Air Dispersion Modelling Approach……………………………………………… 9-63
- Air Contaminants…………………………………………………….. 9-63
- Modelling Domain and Sensitive Receptors…………………… 9-63
- Air Dispersion Modelling Approach……………………………………………… 9-63
- Change in Air Quality……………………………………………………………………………….. 9-62
- Greenhouse Gases of Interest……………………………………. 9-31
- Construction Phase………………………………………………………………….. 9-64
- Considered Emission Sources for Air Dispersion Modelling .9-64
- Emission Parameters Summary………………………………….. 9-64
- Air Dispersion Modelling Results – Construction Phase……. 9-65
- Eastern Section of the WSR………………………………………. 9-67
- Operation Phase……………………………………………………………………… 9-74
- Considered Emission Sources for Air Dispersion Modelling .9-74
- Emission Parameters Summary………………………………….. 9-74
- Air Dispersion Modelling Results – Operation Phase………… 9-75
- Eastern Section of the WSR………………………………………. 9-77
- Change in GHGs……………………………………………………………………………………… 9-81
- Construction Phase………………………………………………………………….. 9-82
- GHG Emission Sources During Construction Phase………… 9-82
- GHG Emissions Calculations for the Construction Phase….. 9-82
- GHG Emissions Results for the Construction Phase………… 9-83
- Operation Phase……………………………………………………………………… 9-84
- GHG Emission Sources During Operation Phase……………. 9-84
- GHG Emissions Calculations for the Operation Phase……… 9-84
- GHG Emissions Results for the Operation Phase……………. 9-84
- Construction Phase………………………………………………………………….. 9-82
- Change in Sound Levels……………………………………………………………………………. 9-85
- Increased Noise During Construction Phase………………………………….. 9-85
- Construction Noise Effects – Blasting…………………………… 9-85
- Construction Noise Effects – Aggregate Extraction Sites…… 9-86
- Construction Noise Effects – General Construction Activities9-92
- Increased Noise During Operation Phase………………………………………. 9-96
- Applicable Noise Guidelines………………………………………. 9-96
- Road Traffic Data…………………………………………………….. 9-98
- Noise Modelling Methods………………………………………….. 9-98
- Operational Noise Modelling Results……………………………. 9-99
- Increased Noise During Construction Phase………………………………….. 9-85
- Change in Vibration Levels………………………………………………………………………. 9-100
- Construction Vibration Effects – Blasting……………………………………… 9-101
- Construction Vibration Effects – General Construction Activities……….. 9-102
- Mitigation Measures………………………………………………………………………………………………. 9-105
- Air Quality…………………………………………………………………………………………….. 9-105
- GHGs………………………………………………………………………………………………….. 9-106
- Noise and Vibration………………………………………………………………………………… 9-107
- Characterization of Net Effects………………………………………………………………………………… 9-110
- Potential Effect Pathways Not Carried Through for Further Assessment……………… 9-112
- Considered Emission Sources for Air Dispersion Modelling .9-64
- Predicted Net Effects…………………………………………………………………………….. 9-113
- Change in Air Quality……………………………………………………………… 9-113
- Change in Air Quality During Construction Phase………….. 9-113
- Change in Air Quality During Operation Phase……………… 9-116
- Change in GHGs…………………………………………………………………… 9-118
- Change in GHGs During Construction Phase……………….. 9-118
- Change in GHGs During Operation Phase…………………… 9-118
- Effects of the Project on Canada’s Carbon Footprint and Carbon Sinks……………………………………………………….. 9-119
- Change in Sound Levels…………………………………………………………. 9-119
- Change in Sound Levels due to Aggregate Extraction Operations During Construction Phase……………………….. 9-119
- Change in Sound Levels due to General Construction
- Change in Air Quality……………………………………………………………… 9-113
Activities During Construction Phase………………………….. 9-120
- Change in Sound Levels due to Vehicle Use of the
Proposed Road During Operation Phase…………………….. 9-120
- Summary…………………………………………………………………………………………….. 9-120
- Determination of Significance…………………………………………………………………………………. 9-122
- Air Quality……………………………………………………………………………………………. 9-122
- Greenhouse Gases (GHGs)…………………………………………………………………….. 9-122
- Noise………………………………………………………………………………………………….. 9-122
- Cumulative Effects………………………………………………………………………………………………. 9-123
- Prediction Confidence in the Assessment………………………………………………………………….. 9-124
- Air Quality……………………………………………………………………………………………. 9-124
- Greenhouse Gases (GHGs)…………………………………………………………………….. 9-124
- Noise and Vibration……………………………………………………………………………….. 9-124
- Predicted Future Condition of the Environment if the Project Does Not Proceed…………………. 9-125
- Climate Change Resilience…………………………………………………………………………………….. 9-125
- Follow-Up and Monitoring………………………………………………………………………………………. 9-126
- Air Quality……………………………………………………………………………………………. 9-126
- Greenhouse Gases (GHGs)…………………………………………………………………….. 9-126
- Noise and Vibration……………………………………………………………………………….. 9-126
- References…………………………………………………………………………………………………………. 9-127
- Determination of Significance…………………………………………………………………………………. 9-122
10. Assessment of Effects on Fish and Fish Habitat………………………………………………………………….. 10-6
- Scope of the Assessment………………………………………………………………………………………… 10-6
- Regulatory and Policy Setting……………………………………………………………………. 10-6
- Consideration of Input from Engagement and Consultation Activities………………….. 10-9
- Incorporation of Indigenous Knowledge and Land and Resource Use Information… 10-17
- Valued Component and Indicators……………………………………………………………… 10-24
- Spatial and Temporal Boundaries………………………………………………………………. 10-26
- Spatial Boundaries…………………………………………………………………. 10-26
- Temporal Boundaries……………………………………………………………… 10-26
- Identification of Project Interactions with Fish and Fish Habitat…………………………. 10-28
- Existing Conditions……………………………………………………………………………………………….. 10-31
- Methods………………………………………………………………………………………………. 10-31
- Desktop Review of Background Information…………………………………. 10-31
- Field Surveys………………………………………………………………………… 10-31
- Fish Habitat and Fish Community Surveys…………………… 10-32
- Spawning Surveys…………………………………………………. 10-35
- Benthic Invertebrate Surveys……………………………………. 10-35
- Environmental DNA (eDNA) Sampling………………………… 10-36
- Species at Risk……………………………………………………………………… 10-36
- Results………………………………………………………………………………………………… 10-37
- Fish Habitat and Fish Community Surveys…………………… 10-37
- Spawning Surveys…………………………………………………. 10-46
- Benthic Invertebrate Surveys……………………………………. 10-46
- Environmental DNA (eDNA) Sampling………………………… 10-46
- Methods………………………………………………………………………………………………. 10-31
- Identification of Potential Effects, Pathways and Indicators…………………………………………….. 10-46
- Changes to Quantity and Quality of Fish Habitat……………………………………………. 10-46
- Destruction/Loss of Fish Habitat………………………………………………… 10-47
- Harmful Alteration and Disruption of Fish Habitat…………………………… 10-49
- Changes in Fish Access to Habitats……………………………………………. 10-52
- Changes to Fish Populations…………………………………………………………………….. 10-54
- Injury/Death of Fish………………………………………………………………… 10-54
- Change in Public Access to Fish/Fish Habitat……………………………….. 10-55
- Changes to Quantity and Quality of Fish Habitat……………………………………………. 10-46
- Mitigation and Enhancement Measures……………………………………………………………………… 10-61
- Changes to Quantity and Quality of Fish Habitat……………………………………………. 10-62
- Destruction/Loss of Fish Habitat………………………………………………… 10-62
- General Avoidance Measures and Project Planning
- Destruction/Loss of Fish Habitat………………………………………………… 10-62
- Changes to Quantity and Quality of Fish Habitat……………………………………………. 10-62
- Spatial and Temporal Boundaries………………………………………………………………. 10-26
and Design…………………………………………………………… 10-62
- Habitat Offsetting and Enhancement………………………….. 10-63
- Harmful Alteration and Disruption of Fish Habitat…………………………… 10-64
- Temporary Watercourse Crossings……………………………. 10-64
- Project Planning and Design…………………………………….. 10-64
- Vegetation Clearing………………………………………………… 10-65
- Storage and Handling of Materials……………………………… 10-66
- Erosion and Sediment Control…………………………………… 10-66
- Harmful Alteration and Disruption of Fish Habitat…………………………… 10-64
- Spill Prevention and Response………………………………….. 10-67
- Dewatering Activities………………………………………………. 10-68
- Air Contaminants and Dust Emissions………………………… 10-69
- Change in Fish Access to Habitats…………………………………………….. 10-69
- Project Planning and Design…………………………………….. 10-69
- Culvert Maintenance and Monitoring…………………………… 10-70
- Changes to Fish Populations…………………………………………………………………….. 10-70
- Injury/Death of Fish………………………………………………………………… 10-71
- Blasting Restrictions……………………………………………….. 10-71
- Restricted Activity Periods / Timing Windows……………….. 10-71
- Work Isolation and Fish Rescue………………………………… 10-72
- Changes to Public Access to Fish Habitats………………………………….. 10-72
- Project Planning and Design…………………………………….. 10-72
- Employee Wildlife Orientations and Restrictions……………. 10-72
- Public Access Restrictions……………………………………….. 10-73
- Injury/Death of Fish………………………………………………………………… 10-71
- Characterization of Net Effects………………………………………………………………………………… 10-96
- Potential Effect Pathways Not Carried Through for Further Assessment……………… 10-97
- Predicted Net Effects………………………………………………………………………………. 10-98
- Changes to Quantity and Quality of Fish Habitat……………………………. 10-98
- Destruction/Loss of Fish Habitat………………………………… 10-98
- Harmful Alteration and Disruption of Fish Habitat…………. 10-100
- Fish Access to Habitats…………………………………………. 10-103
- Changes to Fish Populations…………………………………………………… 10-105
- Injury/Death of Fish………………………………………………. 10-105
- Changes in Public Access to Fish Habitats…………………. 10-107
- Changes to Quantity and Quality of Fish Habitat……………………………. 10-98
- Summary……………………………………………………………………………………………. 10-109
- Determination of Significance…………………………………………………………………………………. 10-111
- Methodology……………………………………………………………………………………….. 10-111
- Results………………………………………………………………………………………………. 10-112
- Destruction/Loss of Fish Habitat………………………………………………. 10-115
- Harmful Alteration and Disruption of Fish Habitat…………………………. 10-115
- Change to Fish Access to Habitats……………………………………………. 10-115
- Injury/Death of Fish……………………………………………………………….. 10-115
- Change in Public Access to Fish Habitat……………………………………. 10-116
- Summary……………………………………………………………………………………………. 10-116
- Cumulative Effects………………………………………………………………………………………………. 10-116
- Prediction Confidence in the Assessment………………………………………………………………….. 10-117
- Predicted Future Condition of the Environment if the Project Does Not Proceed………………… 10-117
- Dewatering Activities………………………………………………. 10-68
- Follow-up and Monitoring……………………………………………………………………………………… 10-117
- References………………………………………………………………………………………………………… 10-119
11. Assessment of Effects on Vegetation and Wetlands – Table of Contents – TO BE PROVIDED
12. Assessment of Effects on Wildlife and Wildlife Habitat – Table of Contents – TO BE PROVIDED
13. Assessment of Effects on Species at Risk – Table of Contents – TO BE PROVIDED
14. Assessment of Effects on Social Environment…………………………………………………………………….. 14-8
- Scope of the Assessment…………………………………………………………………………………………. 14-8
- Regulatory and Policy Setting…………………………………………………………………….. 14-8
- Consideration of Input from Engagement and Consultation Activities………………….. 14-12
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…. 14-19
- Value Components and Indicators……………………………………………………………… 14-20
- Spatial and Temporal Boundaries………………………………………………………………. 14-22
- Spatial Boundaries…………………………………………………………………. 14-23
- Temporal Boundaries……………………………………………………………… 14-24
- Identification of Project Interactions with Social Environment……………………………. 14-26
- Existing Conditions……………………………………………………………………………………………….. 14-31
- Methods………………………………………………………………………………………………. 14-31
- Engagement and Consultation………………………………………………….. 14-31
- Indigenous Knowledge and Land and Resource Use
- Engagement and Consultation………………………………………………….. 14-31
- Methods………………………………………………………………………………………………. 14-31
and Data Validation………………………………………………… 14-32
- Collection and Analysis of Baseline Information…………………………….. 14-32
- Secondary Data Collection……………………………………….. 14-33
- Primary Data Collection…………………………………………… 14-33
- Gender-Based Analysis Plus (GBA+)………………………………………….. 14-34
- GBA+ Data Validation Session………………………………….. 14-34
- Indigenous Knowledge and Land and Resource Use (IKLRU)………….. 14-34
- Summary of Data Sources……………………………………………………….. 14-35
- Results………………………………………………………………………………………………… 14-37
- Population and Demographics…………………………………………………… 14-37
- Housing and Temporary Accommodations…………………………………… 14-46
- Community Services………………………………………………………………. 14-52
- Education, Training and Traditional Learning………………………………… 14-67
- Emergency and Protective Services…………………………………………… 14-86
- Community Infrastructure…………………………………………………………. 14-90
- Community Well-Being and Safety…………………………………………….. 14-97
- Secondary Data Collection……………………………………….. 14-33
- Identification of Potential Effects, Pathways and Indicators……………………………………………. 14-106
- Change to Population and Demographics…………………………………………………… 14-113
- Local Study Area: Webequie First Nation…………………………………… 14-114
- Local Study Area: Other Communities………………………………………. 14-117
- Regional Study Area……………………………………………………………… 14-118
- Change to Housing and Temporary Accommodations…………………………………… 14-119
- Local Study Area: Webequie First Nation…………………………………… 14-120
- Local Study Area: Other Communities………………………………………. 14-123
- Regional Study Area……………………………………………………………… 14-124
- Change to Community Services………………………………………………………………. 14-124
- Local Study Area: Webequie First Nation…………………………………… 14-125
- Local Study Area: Other Communities………………………………………. 14-127
- Regional Study Area……………………………………………………………… 14-127
- Change to Education, Training, and Traditional Learning……………………………….. 14-128
- Local Study Area: Webequie First Nation…………………………………… 14-128
- Local Study Area: Other Communities………………………………………. 14-130
- Regional Study Area……………………………………………………………… 14-132
- Change to Emergency and Protective Services…………………………………………… 14-133
- Local Study Area: Webequie First Nation…………………………………… 14-133
- Local Study Area: Other Communities………………………………………. 14-135
- Regional Study Area……………………………………………………………… 14-135
- Change to Community Infrastructure…………………………………………………………. 14-135
- Local Study Area: Webequie First Nation…………………………………… 14-136
- Local Study Area: Other Communities………………………………………. 14-137
- Regional Study Area……………………………………………………………… 14-138
- Change to Community Well-Being and Safety…………………………………………….. 14-138
- Local Study Area: Webequie First Nation…………………………………… 14-139
- Local Study Area: Other Communities………………………………………. 14-147
- Regional Study Area……………………………………………………………… 14-147
- Summary……………………………………………………………………………………………. 14-148
- Mitigation and Enhancement Measures……………………………………………………………………. 14-149
- Change to Population and Demographics…………………………………………………… 14-149
- Change to Housing and Temporary Accommodations…………………………………… 14-150
- Change to Community Services………………………………………………………………. 14-150
- Change to Education, Training, and Traditional Learning Programming and
- Change to Population and Demographics…………………………………………………… 14-113
Facility Space……………………………………………………………………………………… 14-151
- Change to Emergency and Protective Services…………………………………………… 14-153
- Change to Community Infrastructure…………………………………………………………. 14-155
- Change to Community Well-Being and Safety……………………………………………… 14-156
- Community Cohesion……………………………………………………………. 14-156
- Community Safety………………………………………………………………… 14-158
- Traffic Safety……………………………………………………………………….. 14-159
- Community Well-Being and Quality of Life………………………………….. 14-159
- Summary……………………………………………………………………………………………. 14-160
- Characterization of Net Effects……………………………………………………………………………….. 14-167
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 14-169
- Change to Population and Demographics…………………………………… 14-169
- Change to Housing and Temporary Accommodations…………………… 14-169
- Change to Community Services………………………………………………. 14-169
- Change to Education, Training and Traditional Learning………………… 14-169
- Change to Emergency and Protective Services…………………………… 14-170
- Change to Community Infrastructure…………………………………………. 14-170
- Change to Community Well-Being and Safety…………………………….. 14-170
- Predicted Net Effects…………………………………………………………………………….. 14-170
- Change to Population and Demographics…………………………………… 14-171
- Change to Housing and Temporary Accommodations…………………… 14-172
- Change to Community Services………………………………………………. 14-173
- Change to Education, Training and Traditional Learning………………… 14-174
- Education and Training Attainment…………………………… 14-174
- Availability of Education and Training Programming
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 14-169
and Facility Space………………………………………………… 14-175
- Traditional Learning Programming……………………………. 14-176
- Change to Emergency and Protective Services……………………………. 14-177
- Change to Community Infrastructure…………………………………………. 14-178
- Change to Community Well-Being and Safety……………………………… 14-180
- Change in Community Cohesion……………………………… 14-180
- Change in Community Safety………………………………….. 14-181
- Change in Traffic Safety…………………………………………. 14-182
- Change in Community Well-Being and Quality of Life……. 14-183
- Summary……………………………………………………………………………………………. 14-184
- Determination of Significance…………………………………………………………………………………. 14-186
- Methodology……………………………………………………………………………………….. 14-186
- Results………………………………………………………………………………………………. 14-186
- Population and Demographics…………………………………………………. 14-188
- Housing and Temporary Accommodations…………………………………. 14-188
- Education, Training and Traditional Learning………………………………. 14-188
- Community Services……………………………………………………………… 14-190
- Emergency and protective services…………………………………………… 14-191
- Community Infrastructure……………………………………………………….. 14-191
- Community Well-Being and Safety……………………………………………. 14-192
- Summary……………………………………………………………………………………………. 14-194
- Cumulative Effects………………………………………………………………………………………………. 14-194
- Prediction Confidence in the Assessment…………………………………………………………………. 14-195
- Predicted Future Condition of the Social Environment if the Project Does Not Proceed……….. 14-196
- Follow-Up and Monitoring Programs………………………………………………………………………… 14-198
- References……………………………………………………………………….. Error! Bookmark not defined.
15. Assessment of Effects on Economic Environment……………………………………………………………….. 15-8
- Scope of the Assessment…………………………………………………………………………………………. 15-8
- Regulatory and Policy Setting…………………………………………………………………….. 15-8
- Consideration of Input from Engagement and Consultation Activities………………….. 15-13
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…. 15-20
- Value Components and Indicators……………………………………………………………… 15-25
- Spatial and Temporal Boundaries………………………………………………………………. 15-28
- Spatial Boundaries…………………………………………………………………. 15-28
- Temporal Boundaries……………………………………………………………… 15-29
- Identification of Project Interactions with Economic Environment……………………….. 15-31
- Existing Conditions……………………………………………………………………………………………….. 15-34
- Methods………………………………………………………………………………………………. 15-34
- Engagement and Consultation………………………………………………….. 15-34
- Indigenous Knowledge and Land and Resource Use
- Engagement and Consultation………………………………………………….. 15-34
- Methods………………………………………………………………………………………………. 15-34
(IKLRU) and Data Validation…………………………………….. 15-35
- Collection and Analysis of Baseline Information…………………………….. 15-35
- Secondary Data Collection……………………………………….. 15-36
- Primary Data Collection…………………………………………… 15-36
- Effects Assessment Methods……………………………………. 15-37
- Gender-Based Analysis Plus (GBA+)………………………………………….. 15-38
- GBA+ Data Validation Session………………………………….. 15-39
- Indigenous Knowledge and Land and Resource Use (IKLRU)………….. 15-39
- Summary of Data Sources……………………………………………………….. 15-40
- Results………………………………………………………………………………………………… 15-42
- Labour Force, Employment and Income………………………………………. 15-42
- Labour Force Participation……………………………………….. 15-42
- Labour Income………………………………………………………. 15-52
- Labour Force, Employment and Income………………………………………. 15-42
- Secondary Data Collection……………………………………….. 15-36
- Overall Economy……………………………………………………………………. 15-54
- Cost of Living………………………………………………………… 15-55
- Economic Development…………………………………………… 15-64
- Traditional Indigenous Economy………………………………… 15-72
- Gross Domestic Product………………………………………….. 15-75
- Business Environment…………………………………………………………….. 15-75
- Main Employers…………………………………………………….. 15-75
- Local Economy……………………………………………………… 15-78
- Mining, Aggregate and Forestry Activity………………………. 15-80
- Public and Indigenous Community Finances………………………………… 15-83
- Identification of Potential Effects, Pathways and Indicators…………………………………………….. 15-84
- Change to Labour Force, Employment and Income……………………………………….. 15-92
- Local Study Area: Webequie First Nation…………………………………….. 15-92
- Local Study Area: Other Communities………………………………………… 15-97
- Regional Study Area………………………………………………………………. 15-99
- Change to Overall Economy……………………………………………………………………. 15-106
- Local Study Area: Webequie First Nation…………………………………… 15-108
- Local Study Area: Other Communities……………………………………….. 15-114
- Regional Study Area……………………………………………………………… 15-120
- Change to Business Environment…………………………………………………………….. 15-125
- Local Study Area: Webequie First Nation…………………………………… 15-126
- Local Study Area: Other Communities……………………………………….. 15-128
- Regional Study Area……………………………………………………………… 15-132
- Change to Public and Indigenous Community Finance………………………………….. 15-134
- Local Study Area: Webequie First Nation…………………………………… 15-135
- Local Study Area: Other Communities……………………………………….. 15-135
- Regional Study Area……………………………………………………………… 15-135
- Summary……………………………………………………………………………………………. 15-139
- Change to Labour Force, Employment and Income……………………………………….. 15-92
- Mitigation and Enhancement Measures……………………………………………………………………. 15-139
- Labour Force, Employment, and Income……………………………………………………. 15-140
- Overall Economy………………………………………………………………………………….. 15-141
- Traditional Economy……………………………………………………………… 15-141
- Capacity for Other Projects…………………………………………………….. 15-142
- Business Environment…………………………………………………………………………… 15-142
- Public and Indigenous Community Finances……………………………………………….. 15-143
- Summary……………………………………………………………………………………………. 15-149
- Characterization of Net Effects……………………………………………………………………………….. 15-151
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 15-152
- Predicted Net Effects…………………………………………………………………………….. 15-154
- Cost of Living………………………………………………………… 15-55
- Changes to the Labour Force, Employment and Income………………… 15-154
- Change in the Overall Economy……………………………………………….. 15-155
- Changes in the Business Environment………………………………………. 15-157
- Changes in the Public and Indigenous Community Finances…………… 15-158
- Summary……………………………………………………………………………………………. 15-160
- Determination of Significance…………………………………………………………………………………. 15-161
- Adverse Net Effects………………………………………………………………………………. 15-161
- Positive Net Effects………………………………………………………………………………. 15-162
- Labour Force, Employment and Income…………………………………….. 15-162
- Overall Economy………………………………………………………………….. 15-162
- Business Environment…………………………………………………………… 15-162
- Public and Indigenous Community Finance………………………………… 15-162
- Cumulative Effects………………………………………………………………………………………………. 15-162
- Prediction Confidence in the Assessment………………………………………………………………….. 15-163
- Assumptions……………………………………………………………………………………….. 15-163
- Gaps and Uncertainties………………………………………………………………………….. 15-163
- Predicted Future Condition of the Environment if the Project Does Not Proceed………………… 15-164
- Follow-Up and Monitoring……………………………………………………………………………………… 15-164
- References………………………………………………………………………………………………………… 15-165
16. Assessment of Effects on Non-Traditional Land and Resource Use………………………………………… 16-6
- Scope of the Assessment…………………………………………………………………………………………. 16-7
- Regulatory and Policy Setting…………………………………………………………………….. 16-7
- Consideration of Input from Engagement and Consultation Activities………………….. 16-10
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…. 16-12
- Valued Components and Indicators……………………………………………………………. 16-14
- Spatial and Temporal Boundaries………………………………………………………………. 16-16
- Spatial Boundaries…………………………………………………………………. 16-16
- Temporal Boundaries……………………………………………………………… 16-18
- Identification of Project Interactions with Non-Traditional Land and
Resource Use……………………………………………………………………………………….. 16-18
- Existing Conditions……………………………………………………………………………………………….. 16-23
- Methods………………………………………………………………………………………………. 16-23
- Engagement and Consultation………………………………………………….. 16-23
- Collection and Analysis of Baseline Information…………………………….. 16-23
- Gender Based Analysis Plus (GBA+)………………………………………….. 16-25
- Indigenous Knowledge and Land and Resource Use (IKLRU)………….. 16-25
- Summary of Data Sources……………………………………………………….. 16-26
- Methods………………………………………………………………………………………………. 16-23
- Results………………………………………………………………………………………………… 16-27
- Land Use Context………………………………………………………………….. 16-27
- Land Use Planning and Stewardship………………………………………….. 16-35
- Commercial and Industrial Land Use………………………………………….. 16-59
- Recreation……………………………………………………………………………. 16-80
- Tourism……………………………………………………………………………….. 16-92
- Provincial and Federal Parks, Ontario Areas of Natural and
Scientific Interest and Other Protected Areas……………………………….. 16-99
- Transportation……………………………………………………………………… 16-103
- Identification of Potential Effects, Pathways and Indicators……………………………………………. 16-114
- Change to Land Use Compatibility and Stewardship……………………………………… 16-120
- Local Study Area………………………………………………………………….. 16-120
- Regional Study Area……………………………………………………………… 16-128
- Change to Commercial/Industrial Land Use………………………………………………… 16-132
- Local Study Area………………………………………………………………….. 16-132
- Regional Study Area……………………………………………………………… 16-135
- Change to Recreation and Tourism………………………………………………………….. 16-136
- Local Study Area………………………………………………………………….. 16-137
- Regional Study Area……………………………………………………………… 16-143
- Change to Transportation……………………………………………………………………….. 16-147
- Local Study Area………………………………………………………………….. 16-148
- Regional Study Area……………………………………………………………… 16-151
- Summary……………………………………………………………………………………………. 16-153
- Change to Land Use Compatibility and Stewardship……………………………………… 16-120
- Mitigation and Enhancement Measures……………………………………………………………………. 16-154
- Changes to Land Use Planning and Stewardship…………………………………………. 16-154
- Change to Commercial/Industrial Activities…………………………………………………. 16-157
- Changes to Recreation and Tourism…………………………………………………………. 16-160
- Change to Transportation……………………………………………………………………….. 16-164
- Summary……………………………………………………………………………………………. 16-168
- Characterization of Net Effects……………………………………………………………………………….. 16-171
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 16-173
- Changes to Land Use Planning and Stewardship…………………………. 16-173
- Changes to Commercial/Industrial Activities………………………………… 16-173
- Changes to Recreation and Tourism…………………………………………. 16-173
- Changes to Transportation……………………………………………………… 16-174
- Predicted Net Effects…………………………………………………………………………….. 16-174
- Changes to Recreation and Tourism…………………………………………. 16-175
- Changes to Transportation……………………………………………………… 16-176
- Summary……………………………………………………………………………………………. 16-178
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 16-173
- Identification of Potential Effects, Pathways and Indicators……………………………………………. 16-114
- Determination of Significance…………………………………………………………………………………. 16-180
- Methodology……………………………………………………………………………………….. 16-180
- Results………………………………………………………………………………………………. 16-181
- Recreation and Tourism…………………………………………………………. 16-183
- Transportation……………………………………………………………………… 16-183
- Summary……………………………………………………………………………………………. 16-183
- Cumulative Effects………………………………………………………………………………………………. 16-183
- Prediction of Confidence in the Assessment………………………………………………………………. 16-184
- Predicted Future Condition of the Environment if the Project Does Not Proceed………………… 16-185
- Follow-Up and Monitoring……………………………………………………………………………………… 16-186
- References………………………………………………………………………………………………………… 16-189
17 Assessment of Effects on Human Health…………………………………………………………………………….. 17-5
- Scope of the Assessment…………………………………………………………………………………………. 17-5
- Regulatory and Policy Setting…………………………………………………………………….. 17-5
- Consideration of Input from Engagement and Consultation Activities……………………. 17-8
- Incorporation of Indigenous Knowledge and Human Health Information……………… 17-13
- Valued Component and Indicators……………………………………………………………… 17-13
- What ‘Health’ Means to Webequie First Nation……………………………… 17-13
- Indicators……………………………………………………………………………… 17-14
- Spatial and Temporal Boundaries………………………………………………………………. 17-18
- Spatial Boundaries…………………………………………………………………. 17-18
- Temporal Boundaries……………………………………………………………… 17-19
- Identification of Project Interactions with Human Health………………………………….. 17-20
- Existing Conditions – Baseline Community Health Profile………………………………………………. 17-24
- Methods………………………………………………………………………………………………. 17-24
- Results………………………………………………………………………………………………… 17-25
- Socio-Demographic Profile………………………………………………………. 17-25
- Education…………………………………………………………………………….. 17-25
- Income………………………………………………………………………………… 17-25
- Employment…………………………………………………………………………. 17-25
- Housing……………………………………………………………………………….. 17-26
- Services Provided by Webequie First Nation………………………………… 17-26
- Health Status and Resources……………………………………………………. 17-26
- Spiritual and Cultural Well-Being: Practicing Ceremonies………………… 17-26
- Wellness, Food Security and Healthy Habits………………………………… 17-26
- Racism and Violence………………………………………………………………. 17-26
- Transportation……………………………………………………………………….. 17-27
- Community History…………………………………………………………………. 17-27
- Population Groups Who Maybe Disproportionately Impacted –
a GBA Plus Summary of Baseline Conditions……………………………….. 17-27
- Identification of Potential Effects, Pathways and Indicators…………………………………………….. 17-34
- Assessment Approach…………………………………………………………………………….. 17-34
- Structural / Level 3 Determinants of Health………………………………………………….. 17-45
- Colonization and Trauma from Residential Schools……………………….. 17-45
- Racism and Social Exclusion……………………………………………………. 17-46
- Local Economic Growth…………………………………………………………… 17-47
- Self-Determination and Governance…………………………………………… 17-48
- Worker Accommodations…………………………………………………………. 17-50
- Intermediate / Level 2 Determinants of Health………………………………………………. 17-51
- Air Quality and GHG Emissions…………………………………………………. 17-52
- Noise Levels and Vibration………………………………………………………. 17-53
- Surface Water Quality…………………………………………………………….. 17-55
- Light Pollution and Visual Impact……………………………………………….. 17-57
- Housing……………………………………………………………………………….. 17-59
- Employment and Income…………………………………………………………. 17-61
- Education / Access to Education……………………………………………….. 17-63
- Food Security……………………………………………………………………….. 17-65
- Social Cohesion and Cultural Continuity………………………………………. 17-68
- Safety of Women and Girls………………………………………………………. 17-69
- Traffic Volume and Safety………………………………………………………… 17-70
- Access to Healthcare Services………………………………………………….. 17-71
- Access to Social, Mental Health and Family Services……………………… 17-72
- Access to Transportation Services……………………………………………… 17-73
- Access to Emergency Response Services…………………………………… 17-75
- Childhood Development…………………………………………………………… 17-76
- Proximal / Level 1 Determinants of Health……………………………………………………. 17-77
- Mental Wellness…………………………………………………………………….. 17-77
- Substance Use……………………………………………………………………… 17-80
- Diet…………………………………………………………………………………….. 17-82
- Mitigation and Enhancement Measures……………………………………………………………………… 17-85
- Characterization of Net Effects………………………………………………………………………………… 17-99
- Potential Effect Pathways Not Carried Through for Further Assessment……………. 17-101
- Predicted Net Effects…………………………………………………………………………….. 17-102
- Structural / Level 3 Determinants of Health…………………………………. 17-102
- Intermediate / Level 2 Determinants of Health……………………………… 17-105
- Proximal / Level 1 Determinants of Health………………………………….. 17-110
- Summary……………………………………………………………………………………………. 17-111
- Determination of Significance…………………………………………………………………………………. 17-114
- Cumulative Effects………………………………………………………………………………………………. 17-114
- Prediction Confidence in the Assessment………………………………………………………………….. 17-115
- Predicted Future Condition of the Environment if the Project Does Not Proceed………………… 17-117
- Follow-up and Monitoring……………………………………………………………………………………… 17-117
- References………………………………………………………………………………………………………… 17-121
18 Assessment of Effects on Visual Environment…………………………………………………………………….. 18-4
- Scope of the Assessment…………………………………………………………………………………………. 18-4
- Regulatory and Policy Setting…………………………………………………………………….. 18-4
- Consideration of Input from Engagement and Consultation Activities……………………. 18-5
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…… 18-5
- Valued Component and Indicators……………………………………………………………….. 18-6
- Spatial and Temporal Boundaries……………………………………………………………….. 18-7
- Spatial Boundaries…………………………………………………………………… 18-7
- Temporal Boundaries……………………………………………………………….. 18-7
- Identification of Project Interactions with Visual Environment……………………………. 18-10
- Existing Conditions……………………………………………………………………………………………….. 18-11
- Methods………………………………………………………………………………………………. 18-11
- Information Sources……………………………………………………………….. 18-11
- Visibility Analysis……………………………………………………………………. 18-12
- Identification of Viewsheds from Receptors………………………………….. 18-12
- Results………………………………………………………………………………………………… 18-12
- Landscape Characteristics……………………………………………………….. 18-12
- Viewsheds and Receptors……………………………………………………….. 18-13
- Methods………………………………………………………………………………………………. 18-11
- Identification of Potential Effects, Pathways, and Indicators……………………………………………. 18-16
- Dimensional Visualizations……………………………………………………………………….. 18-17
- Scenic Quality, Viewer Sensitivity and Distance Ratings………………………………….. 18-21
- Project Visibility/Prominence…………………………………………………………………….. 18-22
- Mitigation Measures………………………………………………………………………………………………. 18-25
- Characterization of Net Effects………………………………………………………………………………… 18-27
- Potential Effect Pathways Not Carried Through for Further Assessment……………… 18-28
- Predicted Net Effects………………………………………………………………………………. 18-28
- Change to Visual Landscape Quality During Operations………………….. 18-28
- Summary……………………………………………………………………………………………… 18-29
- Determination of Significance………………………………………………………………………………….. 18-31
- Cumulative Effects………………………………………………………………………………………………… 18-31
- Prediction Confidence in the Assessment…………………………………………………………………… 18-32
- Predicted Future Condition of the Environment if the Project Does Not Proceed…………………. 18-32
- Follow-Up and Monitoring………………………………………………………………………………………. 18-32
- References…………………………………………………………………………………………………………. 18-32
19 Assessment of Effects of the Project on Indigenous Peoples and Impacts to the Exercise of Aboriginal and Treaty Rights – Table of Contents – TO BE PROVIDED
20 Assessment of Effects on Cultural Heritage and Archaeological Resources…………………………….. 20-4
- Scope of the Assessment………………………………………………………………………………………… 20-4
- Regulatory and Policy Setting……………………………………………………………………. 20-4
- Consideration of Input from Engagement and Consultation Activities………………….. 20-7
- Incorporation of Indigenous Knowledge and Land and Resource Use Information….. 20-9
- Valued Component and Indicators…………………………………………………………….. 20-13
- Spatial and Temporal Boundaries……………………………………………………………… 20-14
- Spatial Boundaries………………………………………………………………… 20-14
- Temporal Boundaries…………………………………………………………….. 20-14
- Identification of Project Interactions with Cultural Heritage and Archaeological Resources…………………………………………………………………………………………… 20-16
- Existing Conditions………………………………………………………………………………………………. 20-18
- Methods……………………………………………………………………………………………… 20-18
- Built Heritage Resources and Cultural Heritage Landscapes…………… 20-18
- Archaeological Sites and Resources………………………………………….. 20-19
- Stage 1 Archaeological Assessment………………………….. 20-20
- Stage 2 Archaeological Assessment………………………….. 20-20
- Results……………………………………………………………………………………………….. 20-21
- Built Heritage Resources…………………………………………………………. 20-21
- Cultural Heritage Landscapes………………………………………………….. 20-21
- Archaeological Resources……………………………………………………….. 20-23
- Methods……………………………………………………………………………………………… 20-18
- Identification of Potential Effects, Pathways, and Indicators…………………………………………… 20-25
- Change to Built Heritage Resources and Cultural Heritage Landscapes…………….. 20-25
- Change to Archaeological Resources………………………………………………………… 20-27
- Mitigation Measures……………………………………………………………………………………………… 20-30
- Built Heritage Resources and Cultural Heritage Landscapes…………………………… 20-30
- Archaeological Resources……………………………………………………………………….. 20-31
- Characterization of Net Effects……………………………………………………………………………….. 20-35
- Determination of Significance…………………………………………………………………………………. 20-35
- Cumulative Effects………………………………………………………………………………………………. 20-35
- Prediction Confidence in the Assessment…………………………………………………………………… 20-35
- Predicted Future Condition of the Environment if the Project Does Not Proceed………………….. 20-35
- Follow-Up and Monitoring……………………………………………………………………………………….. 20-35
- References…………………………………………………………………………………………………………. 20-36
21. Cummulative Effects Assessment – Table of Contents – TO BE PROVIDED
22. Follow-up and Monitoring Programs – Table of Contents – TO BE PROVIDED
23. Accidents and Malfunctions……………………………………………………………………………………………… 23-3
- Introduction…………………………………………………………………………………………………………… 23-3
- Scope of Assessment……………………………………………………………………………………………… 23-4
- Regulatory and Policy Setting…………………………………………………………………….. 23-4
- Consideration and Influence of Input Received During Engagement and
- Scope of Assessment……………………………………………………………………………………………… 23-4
Consultation Activities………………………………………………………………………………. 23-6
- Valued Components…………………………………………………………………………………. 23-7
- Assessment Approach…………………………………………………………………………………………….. 23-7
- Description of Accidents and Malfunctions…………………………………………………….. 23-8
- Temporal and Spatial Boundaries……………………………………………………………….. 23-8
- Identification of Potential Effects and Pathways………………………………………………. 23-8
- Risk Evaluation – Likelihood and Consequences…………………………………………….. 23-9
- Description of Accident and Malfunctions and Mitigation Commitments……………………………… 23-10
- Mitigation Commitments for Accident and Malfunctions…………………………………… 23-11
- Management Planning and Mitigation…………………………………………. 23-17
- Spills of Hazardous Material……………………………………………………………………… 23-17
- Fires and Explosions………………………………………………………………………………. 23-18
- Structural Failure……………………………………………………………………………………. 23-19
- Vehicle or Equipment Accidents………………………………………………………………… 23-19
- Mitigation Commitments for Accident and Malfunctions…………………………………… 23-11
- Identification of Potential Effects and Pathways…………………………………………………………… 23-20
- Accidental Spills of Hazardous Materials……………………………………………………… 23-20
- Interaction with Valued Components…………………………………………… 23-21
- Fires and Explosions………………………………………………………………………………. 23-23
- Interaction with Valued Components…………………………………………… 23-23
- Structural Failure……………………………………………………………………………………. 23-28
- Interaction with Valued Components…………………………………………… 23-28
- Vehicle or Equipment Accidents………………………………………………………………… 23-29
- Interaction with Valued Components…………………………………………… 23-30
- Accidental Spills of Hazardous Materials……………………………………………………… 23-20
- Assessment Approach…………………………………………………………………………………………….. 23-7
- Risk Summary and Evaluation…………………………………………………………………………………. 23-31
- References…………………………………………………………………………………………………………. 23-34
24 Effects of the Environment on the Project…………………………………………………………………………… 24-4
- Scope of the Assessment…………………………………………………………………………………………. 24-4
- Project Design………………………………………………………………………………………… 24-5
- Climate and Environmental Hazards That May Affect the Project………………………… 24-5
- Consideration of Input from Engagement and Consultation Activities……………………. 24-6
- Incorporation of Indigenous Knowledge and Land and Resource Use Information…… 24-7
- Approach and Methodology……………………………………………………………………….. 24-9
- Spatial Boundaries…………………………………………………………………………………. 24-18
- Climate and Environmental Conditions………………………………………………………………………. 24-19
- Average Climate Trends………………………………………………………………………….. 24-19
- Extreme Weather Events…………………………………………………………………………. 24-23
- Changing Climate Trends………………………………………………………………………… 24-24
- Hydrology and Hydrogeology……………………………………………………………………. 24-24
- Terrain and Geotechnical Conditions………………………………………………………….. 24-25
- Permafrost……………………………………………………………………………. 24-25
- Erosion………………………………………………………………………………… 24-26
- Geohazards………………………………………………………………………….. 24-26
- Vegetation……………………………………………………………………………………………. 24-26
- Wildfires………………………………………………………………………………………………. 24-26
- Potential Effects and Effect Pathways……………………………………………………………………….. 24-26
- Damage to Project Components………………………………………………………………… 24-27
- Delays in the Project Schedule………………………………………………………………….. 24-28
- Mitigation Measures………………………………………………………………………………………………. 24-30
- Characterization of Net Effects for Effects of the Environment on the Project……………………… 24-31
- Net Effects Description Criteria………………………………………………………………….. 24-31
- Damage to Project Components………………………………………………………………… 24-33
- Delays in the Project Schedule………………………………………………………………….. 24-34
- Summary of Net Effects…………………………………………………………………………… 24-34
- Significance Determination……………………………………………………………………………………… 24-36
- Prediction Confidence in the Assessment…………………………………………………………………… 24-36
- Follow-up and Monitoring……………………………………………………………………………………….. 24-36
- Conclusion………………………………………………………………………………………………………….. 24-37
- References…………………………………………………………………………………………………………. 24-37
25 Project Effects in the Context of Canada’s Ability to Meet Its Environmental Obligations and
Its Climate Change Commitments……………………………………………………………………………………… 25-4
- Federal Environmental Obligations……………………………………………………………………………. 25-4
- Convention on Biological Diversity………………………………………………………………. 25-5
- Amended Recovery Strategy for Woodland Caribou……………………………………….. 25-5
- The Convention on Wetlands of International Importance especially as
Waterfowl Habitat (the Ramsar Convention)………………………………………………….. 25-7
- Convention for the Protection of Migratory Birds in the United States and Canada….. 25-9
- Commitments in Respect of Climate Change………………………………………………………………. 25-10
- Canadian Net-Zero Emissions Accountability Act…………………………………………. 25-10
- Assessment of the Project’s Effects…………………………………………………………………………. 25-10
- References…………………………………………………………………………………………………………. 25-21
- Commitments in Respect of Climate Change………………………………………………………………. 25-10
26 Project Contributions to Sustainability………………………………………………………………………………. 26-3
- Assessment Considerations…………………………………………………………………………………….. 26-3
- Project Context……………………………………………………………………………………………………… 26-4
- Engagement and Consultation………………………………………………………………………………….. 26-5
- Issues of Importance……………………………………………………………………………….. 26-5
- Selection of Valued Components………………………………………………………………… 26-6
- Community Plans…………………………………………………………………………………………………… 26-7
- Community-Based Land Use Plan (2019)……………………………………………………… 26-7
- Webequie Comprehensive Community Plan (2023)…………………………………………. 26-7
- Webequie Community Readiness Plan…………………………………………………………. 26-8
- Compatibility of the Plans with Government Initiatives……………………………………… 26-8
- Planning and Design………………………………………………………………………………………………. 26-9
- Evaluation of Alternatives to the Project…………………………………………………………………….. 26-10
- Sustainability Principles…………………………………………………………………………………………. 26-11
- Principle 1: Interconnectedness and Interdependence of Human-Ecological
Systems……………………………………………………………………………………………… 26-11
- Principle 2: Well-Being of Present and Future Generations……………………………… 26-15
- Principle 3: Consider Positive Effects and Reduce Adverse Effects…………………… 26-16
- Principle 4: Precautionary Principle and Consideration of Uncertainty and
Risk of Irreversible Harm…………………………………………………………………………. 26-18
- Conclusion…………………………………………………………………………………………………………. 26-20
- References…………………………………………………………………………………………………………. 26-21
In Text Figures
Figure 1.1: Project Location………………………………………………………………………………………………………… 1-5
Figure 1.2: Project Main Components……………………………………………………………………………………………. 1-6
Figure 1.3: Location of Ring of Fire Area……………………………………………………………………………………….. 1-14
Figure 1.4: Coordinated Webequie-Federal-Provincial EA/IA Process…………………………………………………. 1-20
Figure 2.1: EA/IA Engagement Activities and Milestones………………………………………………………………….. 2-12
Figure 2.2: Webequie First Nation Three-Tier Consultation Approach………………………………………………….. 2-14
Figure 3.1: 200t Cold Weather Heavy Lift Hoverbarge (2009)………………………………………………………………. 3-8
Figure 3.2: Lockheed Martin LMH-1 Hybrid Heavy Lift Airship……………………………………………………………. 3-10
Figure 3.3: Initial Corridor Alternative Concepts Considered by Webequie Community Members……………….. 3-18
Figure 3.4: Preliminary Preferred Corridor – Alternative Corridor 2C……………………………………………………. 3-34
Figure 3.5: Alternative Routes in the Preferred Corridor……………………………………………………………………. 3-35
Figure 3.6: Route Alternatives for Geotechnical Assessment…………………………………………………………….. 3-38
Figure 3.7: Alternative 2……………………………………………………………………………………………………………. 3-39
Figure 3.8: Alternative 3……………………………………………………………………………………………………………. 3-40
Figure 3.9: Hypothetical Rasterization used in Pangea…………………………………………………………………….. 3-46
Figure 3.10: Baseline Heat Map of Raster Values for All Indicators………………………………………………………. 3-47
Figure 3.11: Preferred Route Alternative Carried Forward into the Environmental Assessment / Impact Assessment……………………………………………………………………………………………………………. 3-51
Figure 3.12: Locations of Alternate Aggregate Sources……………………………………………………………………… 3-59
Figure 3.13: Locations of Options for Supplying Aggregate………………………………………………………………… 3-64
Figure 3.14: Multi-Factor Score Comparison of Options for Supplying Aggregate…………………………………….. 3-66
Figure 3.15: Road Options for Accessing ARA-4………………………………………………………………………………. 3-67
Figure 3.16: Multi-Factor Score Comparison of Road Options for ARA-4……………………………………………….. 3-68
Figure 3.17: Construction Camp Options……………………………………………………………………………………….. 3-69
Figure 3.18: Multi-Factor Score Comparison of Construction Camp Options…………………………………………… 3-70
Figure 4.1: Typical Cross-Section for the Webequie Supply Road………………………………………………………… 4-9
Figure 4.2: Road Foundation in Upland Area…………………………………………………………………………………. 4-10
Figure 4.3: Road Foundation in Lowland Area (Peatlands)………………………………………………………………… 4-11
Figure 4.4: Equalization Culverts in Peatlands……………………………………………………………………………….. 4-12
Figure 4.5: Typical Rest/Maintenance Area – Aerial View………………………………………………………………….. 4-14
Figure 4.6: Typical Maintenance Turnaround Area – Aerial View………………………………………………………… 4-14
Figure 4.7: Typical Composite Bridge Cross-Section……………………………………………………………………….. 4-19
Figure 4.8: Navigational Clearance at Culverts for Small Vessels……………………………………………………….. 4-23
Figure 4.9: Aggregate Resource Area – ARA-2………………………………………………………………………………. 4-26
Figure 4.10: Aggregate Resource Area – ARA-4……………………………………………………………………………….. 4-29
Figure 5.1: Effect Assessment Steps…………………………………………………………………………………………….. 5-7
Figure 5.2: Illustration of the Approach for Collection of Indigenous Knowledge and Land and Resource Use Information……………………………………………………………………………………………………….. 5-10
Figure 6.1: Geology, Terrain, and Soils Study Areas……………………………………………………………………….. 6-18
Figure 6.2: Geological Formations within LSA and RSA……………………………………………………………………. 6-24
Figure 6.3: Ontario Geological Survey’s Quaternary Geology in LSA and RSA………………………………………. 6-26
Figure 6.4: Map of Geochemical and Geotechnical Sampling Sites…………………………………………………….. 6-28
Figure 6.5: Northeastern Ontario Seismic Zone………………………………………………………………………………. 6-30
Figure 6.6: Topographic Map of Project Area…………………………………………………………………………………. 6-33
In Text Figures (Cont’d)
Figure 6.7: Surficial Geology……………………………………………………………………………………………………… 6-34
Figure 6.8: Terrain Mapping………………………………………………………………………………………………………. 6-35
Figure 6.9: Eskers – Potential Aggregate/Rock Sources…………………………………………………………………… 6-39
Figure 6.10: Soil Order……………………………………………………………………………………………………………….. 6-41
Figure 6.11: MECP and JDMA Sampling Locations for Peat and Organics……………………………………………… 6-43
Figure 6.12: Areas of Known Soil Contamination………………………………………………………………………………. 6-48
Figure 7.1: Surface Water Resources Study Areas………………………………………………………………………….. 7-24
Figure 7.2: Surface Water and Sediment Sampling Locations……………………………………………………………. 7-28
Figure 7.3: Waterbody Crossings and their Watersheds…………………………………………………………………… 7-30
Figure 8.1: Groundwater Resources Study Areas…………………………………………………………………………… 8-18
Figure 8.2: Input Parameters for Thornthwaite Model………………………………………………………………………. 8-27
Figure 8.3: Webequie Supply Road Typical Section………………………………………………………………………… 8-29
Figure 8.4: Recommended Aggregate Resources Area – ARA-2………………………………………………………… 8-39
Figure 8.5: Recommended Aggregate Resources Area – ARA-4………………………………………………………… 8-40
Figure 9.1: The Leq Concept……………………………………………………………………………………………………… 9-34
Figure 9.2: Atmospheric Environment Study Areas – Air Quality and Climate Change……………………………… 9-40
Figure 9.3: Atmospheric Environment Study Areas – Noise and Vibration…………………………………………….. 9-41
Figure 9.4: Atmospheric Environment Study Areas – Lighting……………………………………………………………. 9-42
Figure 9.5: Location of Climate and Air Quality Monitoring Stations…………………………………………………….. 9-48
Figure 9.6: Relation between mean TSP concentrations measured in air and mean dust deposition measurements carried out at 12 stations in Quebec City from 1979 to 1982…………………………… 9-56
Figure 9.7: Air Dispersion Modelling Domain…………………………………………………………………………………. 9-72
Figure 9.8: Air Dispersion Modelling Domain (close-up near Webequie)……………………………………………….. 9-73
Figure 9.9: Aggregate Extraction Site ARA-2 – Assumed Noise Source Locations…………………………………. 9-90
Figure 9.10: Aggregate Extraction Site ARA-4 – Assumed Noise Source Locations………………………………….. 9-91
Figure 10.1: Spatial Study Boundaries…………………………………………………………………………………………. 10-27
Figure 10.2: Tertiary Watersheds………………………………………………………………………………………………… 10-33
Figure 10.3: Fish and Fish Habitat Assessment Locations………………………………………………………………… 10-34
Figure 14.1: Social Environment Study Areas………………………………………………………………………………… 14-25
Figure 14.2: Population Age and Gender for Webequie First Nation, 2021…………………………………………….. 14-39
Figure 14.3: Population Forecast by Self-Identified Gender for Other Local Study Area Indigenous
Communities (2016, 2021, 2028, 2033, 2043)……………………………………………………………….. 14-41
Figure 14.4: Kenora District – Population Forecast by Self-Identified Gender (2016, 2021, 2028,
2033, 2043)…………………………………………………………………………………………………………… 14-43
Figure 14.5: Thunder Bay District – Population Forecast by Self-Identified Gender (2016, 2021, 2028,
2033, 2043)…………………………………………………………………………………………………………… 14-44
Figure 14.6: Cochrane District – Population Forecast by Self-Identified Gender (2016, 2021, 2028,
2033, 2043)…………………………………………………………………………………………………………… 14-45
Figure 14.7: Private Occupied Private Dwellings by Tenure in Other Local Study Area Indigenous
Communities (2021)………………………………………………………………………………………………… 14-49
Figure 14-8: Highest Certificate, Diploma or Degree for the Population Aged 15 Years and Over in Private Households, Other LSA Indigenous Communities (2021)…………………………………………………. 14-75
In Text Figures (Cont’d)
Figure 14.9: CWB Index Score for Webequie First Nation Compared to the First Nations in
Ontario Average and First Nations Average in Canada…………………………………………………….. 14-99
Figure 14.10: Survey Results from Respondents When Asked If They Have Safety Concerns About
the Project – WSR Socio-Economic Survey…………………………………………………………………. 14-101
Figure 14.11: Safety Concerns Identified by the Community……………………………………………………………… 14-102
Figure 14.12: Road Safety Concerns Identified by the Community………………………………………………………. 14-103
Figure 14.13: Project-Related Population Impact on Webequie First Nation, Construction Phase……………….. 14-115
Figure 14.14: Project-Related Temporary Accommodations Requirements, Construction Phase………………… 14-121
Figure 15.1: Regional and Local Economy Study Areas……………………………………………………………………. 15-30
Figure 15.2: Hours per week spent on domestic and care work- Webequie First Nation…………………………… 15-46
Figure 15.3: CPI across Canada, Ontario and Thunder Bay (2017 = 1.0)……………………………………………… 15-61
Figure 15.4: FTE Project Labour Participation, Regional Study Area, Construction Phase………………………. 15-101
Figure 15.5: Project Labour Requirements Compared to Regional Study Area Workforce by NOC……………. 15-102
Figure 15.6: Project Effect on GDP for Webequie First Nation, Construction Phase………………………………. 15-110
Figure 15.7: Project Effects on GDP, Other Local Study Area Communities, Construction Phase……………… 15-116
Figure 15.8: Construction Phase Total Economic Effect of Project Expenditure on the Regional Study
Area by Year………………………………………………………………………………………………………… 15-120
Figure 16.1: Local Study Area and Regional Study Area for Non-Traditional Land and Resource Use…………. 16-17
Figure 16.2: Treaty Lands and Indigenous Communities…………………………………………………………………… 16-30
Figure 16.3: First Nations Areas of Interest for Planning based on Available Community Based Land Use
Planning Documentation………………………………………………………………………………………….. 16-37
Figure 16.4: Webequie First Nation Three-Tier Model……………………………………………………………………… 16-39
Figure 16.5: Webequie First Nation On-Reserve Land Use Plan – What Will We Build Where?………………….. 16-41
Figure 16.6: Webequie First Nation On-Reserve Land Use Plan – Future Roads map…………………………….. 16-42
Figure 16.7: Webequie Concepts of Comprehensive Community Plan…………………………………………………. 16-44
Figure 16.8: Marten Falls First Nation Area of Interest for Planning…………………………………………………….. 16-48
Figure 16.9: Attawapiskat First Nation Area of Interest for Planning…………………………………………………….. 16-49
Figure 16.10: Eabametoong First Nation and Mishkeegogamang First Nation Area of Interest for Planning……. 16-50
Figure 16.11: Weenusk First Nation Area of Interest for Planning…………………………………………………………. 16-57
Figure 16.12: Existing Mining Claims and Tenure in the LSA and RSA………………………………………………….. 16-66
Figure 16.13: Existing Aggregate Deposits in the LSA and RSA…………………………………………………………… 16-68
Figure 16.14: Existing Aggregate Deposits in the Project Footprint………………………………………………………. 16-69
Figure 16.15: Transmission and Power Lines in Northern Ontario…………………………………………………………. 16-79
Figure 16.16: Outposts in the RSA………………………………………………………………………………………………… 16-84
Figure 16.17: Map of Region 13c Northwest Ontario Regional Tourism Organization………………………………… 16-98
Figure 16.18: Provincial Parks, Ontario ANSI in the RSA…………………………………………………………………. 16-102
Figure 16.19: Webequie Winter Road Routes………………………………………………………………………………… 16-104
Figure 17.1: Contributing sources to the development of the human health effect assessment of the
social and environmental determinants of health……………………………………………………………. 17-35
Figure 18.1: Visual Environment Study Areas………………………………………………………………………………….. 18-9
Figure 18.2: Potential Receptor Locations…………………………………………………………………………………….. 18-15
Figure 18.3: Winisk Lake Crossing – Pre-Construction – Viewing South………………………………………………. 18-18
Figure 18.4: Winisk Lake Crossing – Post-Construction – Viewing South……………………………………………… 18-18
Figure 18.5: Winisk Lake Crossing – Post-Construction – Viewing West………………………………………………. 18-18
In Text Figures (Cont’d)
Figure 18.6: Winiskisis Channel Crossing – Pre-Construction – Viewing West……………………………………….. 18-19
Figure 18.7: Winiskisis Channel Crossing – Post-Construction – Viewing West……………………………………… 18-19
Figure 18.8: Winiskisis Channel Crossing – Post-Construction – Viewing South…………………………………….. 18-19
Figure 18.9: Muketei River Crossing – Pre-Construction – Viewing South…………………………………………….. 18-20
Figure 18.10: Muketei River Crossing – Post-Construction – Viewing South……………………………………………. 18-20
Figure 18.11: Muketei River Crossing – Post-Construction – Viewing West…………………………………………….. 18-20
Figure 20.1: Cultural Heritage and Archaeological Resources Study Areas…………………………………………… 20-15
Figure 24.1: Location of Climate and Air Quality Monitoring Stations…………………………………………………… 24-21
Figure 24.2: Climate Norms (1971-2000) at Lansdowne House Meteorological Station (ECCC, 2024)…………. 24-22
Figure 24.3: Mean Annual Temperature and Total Annual Precipitations over Several Decades at the
Pickle Lake Meteorological Station (ECCC, 2024)…………………………………………………………… 24-22
Figure 26.1: Interdependence and Interconnectedness of Valued Components within a Human-Ecological
System………………………………………………………………………………………………………………… 26-12
Figure 26.2: Interconnectedness of VCs with the Human Health VC……………………………………………………. 26-14
In-Text Tables
Table 1-1: Proponent Contact Information……………………………………………………………………………………… 1-7
Table 1-2: Federal Legislation, Permits, and Other Authorizations……………………………………………………… 1-20
Table 1-3: Provincial Legislation, Permits, and Other Authorizations…………………………………………………… 1-21
Table 2-1: Indigenous Communities Consulted and Engaged…………………………………………………………….. 2-9
Table 2-2: Indigenous Engagement and Consultation Methods During the EA/IA…………………………………… 2-17
Table 2-3: Monthly Newsletters Circulated During EA/IA Process………………………………………………………. 2-22
Table 2-4: Consultation Activities Conducted During Consultation Round 1………………………………………….. 2-27
Table 2-5: Consultation Activities Conducted During Consultation Round 2………………………………………….. 2-30
Table 2-6: Consultation Activities Conducted During Consultation Round 3………………………………………….. 2-35
Table 2-7: Key Issues and Concerns Raised by Indigenous Communities and Groups from Engagement
and Consultation Activities…………………………………………………………………………………………. 2-40
Table 2-8: Public and Stakeholder Engagement Methods During the EA/IA Process………………………………. 2-53
Table 2-9: Notices to the Public and Stakeholders During the EA/IA Process……………………………………….. 2-54
Table 2-10: Select Provincial and Federal Agencies Technical Comments and/or Concerns on Study Plans…. 2-58
Table 2-11: Select Provincial and Federal Agencies Comments and/or Concerns on Draft Natural
Environment Existing Conditions Report………………………………………………………………………… 2-62
Table 2-12: Select Provincial and Federal Agencies Comments and/or Concerns on Draft Socio-Economic Existing Conditions Report…………………………………………………………………………………………. 2-66
Table 2-13: Select Provincial and Federal Agencies Comments on the Alternatives Assessment
(Consultation Round 2)………………………………………………………………………………………………. 2-68
Table 2-14: Issues and/or Concerns Raised by the Public and Other Stakeholders…………………………………. 2-69
Table 3-1: Screening Factor for Alternatives to the Undertaking………………………………………………………….. 3-6
Table 3-2: Chronological Summary of Historical Studies…………………………………………………………………. 3-14
Table 3-3: MECP Code of Practice for Determining a Reasonable Range of Alternative Methods……………… 3-20
Table 3-4: Webequie Community-Based Considerations for Screening Alternative Corridors……………………. 3-24
Table 3-5: Additional Considerations Used in Screening Alternative Supply Road Corridors…………………….. 3-26
In Text Tables (Cont’d)
Table 3-6: Summary Comparative Analysis of Supply Road Corridor Alternative Concepts – Screening
Level Assessment…………………………………………………………………………………………………….. 3-29
Table 3-7: Factors, Disciplines, and Criteria………………………………………………………………………………….. 3-44
Table 3-8: Comparison of Route Alternatives at the Category Level and Overall……………………………………. 3-48
Table 3-9: Comparison of Route Alternatives at the Criteria Level………………………………………………………. 3-49
Table 3-10: Sensitivity Run 1………………………………………………………………………………………………………. 3-53
Table 3-11: Sensitivity Run 2………………………………………………………………………………………………………. 3-55
Table 3-12: Locations of Alternate Aggregate Sources………………………………………………………………………. 3-57
Table 3-13: Summary of Aggregate Requirements…………………………………………………………………………… 3-63
Table 3-14: Alternate Aggregate Source Screening Criteria………………………………………………………………… 3-65
Table 4-1: Preliminary Design Criteria for the Project………………………………………………………………………… 4-6
Table 4-2: Waterbody Crossings and Proposed Structure Type for the Webequie Supply Road………………… 4-17
Table 4-3: Crossings of Navigable Waterways……………………………………………………………………………….. 4-23
Table 4-4: Temporary and Permanent Support Infrastructure…………………………………………………………….. 4-24
Table 4-5: Aggregate/Rock/Fill Requirements………………………………………………………………………………… 4-24
Table 4-6: Volume of Aggregate Material at ARA-2…………………………………………………………………………. 4-27
Table 4-7: Volume of Aggregate Material at ARA-4…………………………………………………………………………. 4-30
Table 4-8: Summary of Expected Equipment and Vehicles Used for Project Construction………………………… 4-49
Table 4-9: Summary of Expected Equipment and Vehicles Used for Project Operations Activities……………… 4-72
Table 4-10: Summary of Estimated Employment for Project Construction………………………………………………. 4-75
Table 4-11: Summary of Estimated Employment Per Year for Project Operations……………………………………. 4-82
Table 5-1: Project Interactions with (VC Name) and Potential Effects………………………………………………….. 5-12
Table 5-2: Baseline Study Appendices…………………………………………………………………………………………. 5-14
Table 5-3: Potential Effects, Pathways and Indicators for (VC Name)………………………………………………….. 5-15
Table 5-4: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for (VC Name)…….. 5-16
Table 5-5: Criteria for Characterization of Predicted Net Effects on (VC name)……………………………………… 5-18
Table 5-6: Summary Example of Predicted Net Effects on [VC name]…………………………………………………. 5-19
Table 6-1: Key Regulation, Legislation, Policy Relevant to Geology, Terrain and Soils……………………………… 6-6
Table 6-2: Geology, Terrain, and Soils VC – Summary of Inputs Received During Engagement and
Consultation………………………………………………………………………………………………………………. 6-9
Table 6-3: Geology, Terrain, and Soils VC – Summary of Indigenous Knowledge and Land and
Resource Use Information…………………………………………………………………………………………… 6-14
Table 6-4: Geology, Terrain, and Soils VC – Subcomponents, Indicators, and Rationale…………………………. 6-17
Table 6-5: Project Interactions with Geology, Terrain, and Soils VC and Potential Effects………………………… 6-19
Table 6-6: Lithology in the Project Area………………………………………………………………………………………… 6-25
Table 6-7: Geochemical Sampling Sites……………………………………………………………………………………….. 6-27
Table 6-8: Summary of ABA and SPLP Test Results for 2020 Geochemical Sampling……………………………. 6-27
Table 6-9: Summary of Borehole Locations and Elevations……………………………………………………………….. 6-44
Table 6-10: Summary of Soil Analytical Laboratory Results………………………………………………………………… 6-44
Table 6-11: Potential Effects, Pathways and Indicators for Geology, Terrain, and Soils VC………………………… 6-52
Table 6-12: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for Geology,
Terrain, and Soils VC…………………………………………………………………………………………………. 6-55
Table 6-13: Criteria for Characterization of Predicted Net Effects on Geology, Terrain, and Soils VC……………. 6-61
In Text Tables (Cont’d)
Table 6-14: Affected Geological Features in the Project Footprint Relative to the Amount Present in the
LSA and RSA………………………………………………………………………………………………………….. 6-64
Table 6-15: Summary of Predicted Net Effects on Geology, Terrain, and Soils VC………………………………….. 6-66
Table 6-16: Scores Assigned for Key Criteria (Categories) of the Predicted Net Effects……………………………. 6-67
Table 6-17: Key Criteria and Scores for Determining the Significance of the Predicted Net Adverse Effects
on Geology, Terrain, and Soils VC……………………………………………………………………………….. 6-69
Table 7-1: Key Regulation, Legislation, Policy Relevant to Surface Water Resources Assessment for
the Project……………………………………………………………………………………………………………….. 7-6
Table 7-2: Surface Water Resources VC – Summary of Inputs Received During Engagement and
Consultation……………………………………………………………………………………………………………… 7-9
Table 7-3: Surface Water Resources VC – Summary of Indigenous Knowledge and Land and Resource
Use Information……………………………………………………………………………………………………….. 7-17
Table 7-4: Surface Water Resources VC – Subcomponents, Indicators, and Rationale…………………………… 7-22
Table 7-5: Project Interactions with Surface Water Resources VC and Potential Effects…………………………. 7-25
Table 7.6: Water Quality Sampling Sites……………………………………………………………………………………… 7-32
Table 7-7: Surface Water Quality – Summary of Field Measuring and Laboratory Analytical Parameters Collected in 2019, 2020, 2021, and 2023……………………………………………………………………….. 7-32
Table 7-8: Sediment Quality Sampling Sites…………………………………………………………………………………. 7-33
Table 7-9: Sediment Quality – Summary of Field Measuring and Laboratory Analytical Parameters
Collected in 2020……………………………………………………………………………………………………… 7-34
Table 7-10: Summary of Analytical Results for Water Quality in the Winisk River Watershed……………………… 7-36
Table 7-11: Summary of Analytical Results for Water Quality in the Ekwan River Watershed…………………….. 7-38
Table 7-12: Summary of Analytical Results for Water Quality in the Attawapiskat River Watershed……………… 7-41
Table 7-13: Potential Effects, Pathways, and Indicators for Surface Water Resources VC………………………… 7-49
Table 7-14: Summary of Potential Effects, Mitigation Measures, and Predicted Net Effects for Surface Water Resources VC………………………………………………………………………………………………… 7-57
Table 7-15: Criteria for Characterization of Predicted Net Effects on Surface Water Resources VC…………….. 7-67
Table 7-16: Summary of Predicted Net Effects on Surface Water Resources VC…………………………………….. 7-74
Table 8-1: Key Regulation, Legislation, Policy Relevant to Groundwater Resources………………………………… 8-6
Table 8-2: Groundwater Resources VC – Summary of Input Received During Engagement and Consultation 8-8
Table 8-3: Groundwater Resources VC – Summary of Indigenous Knowledge and Land and Resource
Use Information……………………………………………………………………………………………………….. 8-12
Table 8-4: Groundwater Resources VC – Subcomponents, Indicators, and Rationale…………………………….. 8-16
Table 8-5: Project Interactions with Groundwater Resources VC and Potential Effects…………………………… 8-19
Table 8-6: Infiltration Factors – Pre-Development…………………………………………………………………………… 8-28
Table 8-7: Annual Infiltration Volumes – Pre-Development Road Right-of-Way (Previous Areas)………………. 8-30
Table 8-8: Annual Infiltration Volumes – Post-Development Road Right-of-Way (Pervious Areas)……………… 8-30
Table 8-9: Changes to Annual Infiltration Volumes – Pre- and Post-Development Road Right-of-Way……….. 8-31
Table 8-10: ABA Results for Rock Samples…………………………………………………………………………………… 8-33
Table 8-11: ABA Results for Soil Samples…………………………………………………………………………………….. 8-33
Table 8-12: Input Parameters for Dewatering Assessment – Structure………………………………………………….. 8-35
Table 8-13: Results of Dewatering Assessment – Each Structure Foundation………………………………………… 8-36
Table 8-14: Input Parameters for Dewatering Assessment – Aggregate Resources Area (ARA-2)……………….. 8-37
Table 8-15: Results of Dewatering Assessment – Aggregate Resources Area (ARA-2)…………………………….. 8-38
In Text Tables (Cont’d)
Table 8-16: Input Parameters for Dewatering Assessment – Water Supply Wells……………………………………. 8-41
Table 8-17: Summary of Potential Effects, Pathways, and Indicators for Groundwater Resources VC………….. 8-44
Table 8-18: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Groundwater Resources VC……………………………………………………………………………………….. 8-50
Table 8-19: Criteria for Characterization of Predicted Net Effects on Groundwater Resources VC……………….. 8-53
Table 8-20: Summary of Predicted Net Effects on Groundwater Resources VC………………………………………. 8-58
Table 8-21: cores Assigned for Key Criteria (Categories) of the Predicted Net Effects……………………………… 8-60
Table 8-22: Key Criteria and Scores for Determining the Significance of the Predicted Net Adverse Effects on Groundwater Resources VC……………………………………………………………………………………. 8-62
Table 9-1: Key Regulation, Legislation, Policy Relevant to Air Quality…………………………………………………… 9-8
Table 9-2: Key Regulation, Legislation, Policy Relevant to GHG Emissions Assessment for the Project……… 9-10
Table 9-3: Key Regulation, Legislation, Policy Relevant to Noise and Vibration Assessment for the Project…. 9-11
Table 9-4: Atmospheric Environment VC – Summary of Inputs Received During Engagement and
Consultation……………………………………………………………………………………………………………. 9-13
Table 9-5: Atmospheric Environment VC – Summary of Indigenous Knowledge and Land and Resource
Use Information……………………………………………………………………………………………………….. 9-25
Table 9-6: Ambient Air Quality Criteria and Standards for Contaminants of Interest……………………………….. 9-30
Table 9-7: Emission Factors Considered in the GHG Emissions Assessment………………………………………. 9-32
Table 9-8: Range of Sound Levels……………………………………………………………………………………………… 9-33
Table 9-9: Subjective Human Perception of Changes in Sound Levels………………………………………………… 9-35
Table 9-10: Atmospheric Environment VC – Subcomponents, Indicators, and Rationale…………………………… 9-37
Table 9-11: Project Interactions with Atmospheric Environment VC and Potential Effects…………………………. 9-43
Table 9-12: Ambient Air Quality Monitoring Stations Reviewed…………………………………………………………… 9-47
Table 9-13: Estimations of Background Sound Levels Using Qualitative Descriptions and Population Densities
of Average Types of Communities (from Health Canada Guidelines)……………………………………. 9-51
Table 9-14: Summary of Background Concentrations for Studied Contaminants…………………………………….. 9-54
Table 9-15: Overview of Existing GHG Emission Sources in the Webequie Community……………………………. 9-57
Table 9-16: Summary of Measured Background Ambient Sound Levels at Monitors M1, M2, and M3………….. 9-59
Table 9-17: Summary of Background Sound Levels for Use in the Assessment……………………………………… 9-61
Table 9-18: Maximum Concentrations for CACs Calculated in Air During the Construction Phase
(without mitigation measures)………………………………………………………………………………………. 9-67
Table 9-19: Maximum Concentrations for Other Contaminants Calculated in Air During the Construction
Phase (without mitigation measures)…………………………………………………………………………….. 9-68
Table 9-20: Maximum Concentrations (with mitigation measures in place) for Contaminants for Which the Construction Phase Generates Substantial Concentrations in Air (without mitigation measures)…. 9-69
Table 9-21: Maximum Concentration for Contaminants Calculated in Air in Areas of Interest During the Construction Phase (with mitigation measures)……………………………………………………………….. 9-70
Table 9-22: Maximum Concentrations for CACs Calculated in Air During the Operation Phase
(without dust control)…………………………………………………………………………………………………. 9-77
Table 9-23: Maximum Concentrations for Other Contaminants Calculated in Air During the Operation Phase (without dust control)…………………………………………………………………………………………………. 9-78
Table 9-24: Maximum Concentrations of Certain Contaminants Calculated in Air During the Operation Phase (with dust control)………………………………………………………………………………………….. 9-79
In Text Tables (Cont’d)
Table 9-25: Maximum Concentration for Contaminants Calculated in Air in Areas of Interest During the
Operation Phase (with dust control)……………………………………………………………………………… 9-80
Table 9-26: GHG Emissions per Source and Year of Realization for the Construction Phase……………………… 9-83
Table 9-27: Annual GHG Emissions per Source for the Operation Phase………………………………………………. 9-84
Table 9-28: Construction Phase Blasting Noise Guidelines………………………………………………………………… 9-86
Table 9-29: Construction Phase Overpressure Sound Level Limits………………………………………………………. 9-86
Table 9-30: MECP Publication NPC-300 Exclusion Limits for Class 3 Rural Areas…………………………………… 9-87
Table 9-31: Predicted Stationary Sound Levels – Aggregate Extraction Site Operations…………………………… 9-92
Table 9-32: Construction Phase Noise Guidelines……………………………………………………………………………. 9-93
Table 9-33: Construction Mitigation Noise Level (MNL) Corrections……………………………………………………… 9-93
Table 9-34: Construction Equipment…………………………………………………………………………………………….. 9-94
Table 9-35: Operations Phase Noise Guidelines……………………………………………………………………………… 9-96
Table 9-36: MTO Environmental Guide for Noise…………………………………………………………………………….. 9-97
Table 9-37: 2041 “Build” Traffic Information at Anticipated Date of Construction……………………………………… 9-98
Table 9-38: Construction Phase Vibration Guidelines……………………………………………………………………… 9-101
Table 9-39: Construction Phase Vibration Limits……………………………………………………………………………. 9-101
Table 9-40: City of Toronto By-Law Vibration Guidelines………………………………………………………………….. 9-102
Table 9-41: Summary of Zone of Influence (ZOI) Setback Distances Associated with Construction Activities .9-102 Table 9-42: Potential Effects, Pathways and Indicators for Atmospheric Environment VC………………………… 9-104
Table 9-43: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for Atmospheric Environment VC……………………………………………………………………………………………………… 9-108
Table 9-44: Criteria for Characterization of Predicted Net Effects on Atmospheric Environment VC……………. 9-110
Table 9-45: Air Dispersion Modelling Results for the Construction Phase…………………………………………….. 9-114
Table 9-46: Air Dispersion Modelling Results for the Operation Phase………………………………………………… 9-117
Table 9-47: Summary of Predicted Net Effects on Atmospheric Environment VC…………………………………… 9-121
Table 14-1: Key Regulations, Legislation, and Policies relevant to Social Environment Assessment for
the Project……………………………………………………………………………………………………………… 14-9
Table 14-2: Social Environment – Summary of Inputs Received During Engagement and Consultation………. 14-13
Table 14-3: Social Environment VCs – Summary of Indigenous Knowledge…………………………………………. 14-19
Table 14-4: Social Environment VCs –Indicators and Rationale…………………………………………………………. 14-21
Table 14-5: Project Interactions with Social Environment VCs and Potential Effects………………………………. 14-27
Table 14-6: Indigenous Communities Engaged/Consulted……………………………………………………………….. 14-31
Table 14-7: Summary of Methods Data Sources for Social Environment VCs……………………………………….. 14-36
Table 14-8: Registered Population Projection, Webequie First Nation Comprehensive Community
Plan, 2023…………………………………………………………………………………………………………….. 14-37
Table 14-9: Population for Other Local Study Area Indigenous Communities (2021)……………………………….. 14-40
Table 14-10: Regional Study Area Population Forecast (2016, 2021, 2028, 2033, 2043)…………………………… 14-42
Table 14-11: Housing Availability, Webequie First Nation, 2020…………………………………………………………… 14-47
Table 14-12: Private Dwelling Conditions, Webequie First Nation, 2020………………………………………………… 14-48
Table 14-13: Total Private Dwellings and Occupied Private Dwellings in Other Local Study Area
Indigenous Communities (2021)…………………………………………………………………………………. 14-48
Table 14-14: Community Services Availability, Attawapiskat First Nation………………………………………………. 14-56
Table 14-15: Community Services Availability, Eabametoong First Nation…………………………………………….. 14-57
Table 14-16: Community Services Availability, Kasabonika Lake First Nation…………………………………………. 14-59
In Text Tables (Cont’d)
Table 14-17: Community Services Availability, Marten Falls First Nation……………………………………………….. 14-60
Table 14-18: Community Services Availability, Neskantaga First Nation………………………………………………… 14-62
Table 14-19: Community Services Availability, Nibinamik First Nation…………………………………………………… 14-64
Table 14-20: Community Services Availability, Weenusk First Nation…………………………………………………… 14-65
Table 14-21: Highest Certificate, Diploma or Degree for the Population Aged 15 Years and Over in
Private Households in Webequie First Nation (2021)……………………………………………………….. 14-69
Table 14-22: Highest Certificate, Diploma or Degree for the Population Aged 15 Years and Over in
Private Households in Webequie First Nation (2021)……………………………………………………….. 14-71
Table 14-23: Education and Training Facilities Availability, Local Study Area…………………………………………. 14-73
Table 14-24: Educational Attainment within Project-Related Fields, Local Study Area………………………………. 14-76
Table 14-25: Education and Training Facilities and Services in the Regional Study Area Municipalities,
Cities and Towns……………………………………………………………………………………………………. 14-89
Table 14-26: Description of Community Infrastructure in Webequie First Nation……………………………………… 14-91
Table 14-27: Description of Community Infrastructure in Other LSA Indigenous Communities……………………. 14-93
Table 14-28: Description of Community Infrastructure in the RSA………………………………………………………… 14-95
Table 14-29: CWB Index Scores for Indigenous Communities in the LSA…………………………………………….. 14-104
Table 14-30: Crime Statistics in Indigenous Communities and Municipalities for 2021, as Reported by
the Police Service Responsible for that Area……………………………………………………………….. 14-104
Table 14-31: CWB Index Scores for Communities within the Regional Study Area…………………………………. 14-105
Table 14-32: Summary of Potential Effects, Mitigation and Enhancement Measures and Predicted
Net Effects for Social Environment VCs……………………………………………………………………… 14-107
Table 14-33: Project-Related Population Impact on Webequie First Nation, Construction Phase……………….. 14-114
Table 14-34: Increase in Webequie First Nation Population Attributed to the Temporary In-Migration
of Workers from the Other Local Study Area Communities, Construction Phase………………….. 14-117
Table 14-35: Temporary Population Increase in Webequie First Nation Attributed to the Regional Study
Area, Construction Phase……………………………………………………………………………………….. 14-118
Table 14-36: Project-Related Temporary Accommodations Requirements, Construction Phase………………… 14-121
Table 14-37: Local Study Area Community Locations in Relation to Webequie First Nation……………………… 14-123
Table 14-38 Summary and Conclusion of Potential Effects for the Social Environment VCs…………………….. 14-148
Table 14-39: Summary of Potential Effects, Mitigation and Enhancement Measures and Predicted
Net Effects for Social Environment VCs……………………………………………………………………… 14-161
Table 14-40: Criteria for Characterization of Predicted Net Effects on Social Environment VCs………………… 14-167
Table 14-41: Summary of Predicted Net Effects on Social Environment VCs………………………………………… 14-185
Table 14-42: Determination of Significance for the Social Environment VCs…………………………………………. 14-187
Table 15-1: Key Regulation, Legislation, Policy Relevant to Regional and Local Economy………………………… 15-9
Table 15-2: Regional and Local Economy VC – Summary of Input Received During Engagement and Consultation………………………………………………………………………………………………………….. 15-14
Table 15-3: Regional and Local Economy VC – Summary of Indigenous Knowledge and Land and
Resource Use Information………………………………………………………………………………………… 15-21
Table 15-4: Regional and Local Economy VC – Subcomponents, Indicators, and Rationale…………………….. 15-26
Table 15-5: Project Interactions with Regional and Local Economy VC and Potential Effects…………………… 15-31
Table 15-6: Indigenous Communities Engaged/Consulted……………………………………………………………….. 15-34
Table 15-7: Summary of Methods Data Sources for Regional and Local Economic VC…………………………… 15-40
In Text Tables (Cont’d)
Table 15-8: Projected Working Age Population in Webequie First Nation (2016, 2021, 2028, 2033, 2043)…… 15-43
Table 15-9: Existing Employment within National Occupation Code Categories, Webequie First
Nation, 2022………………………………………………………………………………………………………….. 15-44
Table 15-10: Projected Working Age Population for Other LSA Indigenous Communities
(2016, 2021, 2028, 2033, 2043)………………………………………………………………………………….. 15-47
Table 15-11: Existing Employment within National Occupation Code Categories, Local Study Area, 2022…….. 15-49
Table 15-12: Other Local Study Area Unemployment Rate, 2016 and 2021……………………………………………. 15-49
Table 15-13: Cost of the RNFB for a family of four for one month………………………………………………………… 15-59
Table 15-14: Cost of household items, 2016…………………………………………………………………………………… 15-60
Table 15-15: LICO Low-income Status, Cochrane District, 2020………………………………………………………….. 15-62
Table 15-16: LICO Low-income Status, Kenora District, 2020…………………………………………………………….. 15-62
Table 15-17: LICO Low-income Status, Thunder Bay District, 2020……………………………………………………… 15-63
Table 15-18: Do you Have Concerns About the Loss of Traditional Culture in Webequie First Nation?…………. 15-73
Table 15-19: If you Have Concerns About the Loss of Traditional Culture in Webequie First Nation,
What are Those Concerns?………………………………………………………………………………………. 15-73
Table 15-20: All Industry Presence in Webequie First Nation (2018 – 2022)…………………………………………… 15-76
Table 15-21: All Industry Presence in Other LSA Indigenous Communities (2018 – 2022)…………………………. 15-77
Table 15-22: Regional Requirements/ Needs to Meet Demand by Industry in Webequie (2020)………………….. 15-78
Table 15-23: Potential Effects, Pathways and Indicators for Regional and Local Economy
Valued Component…………………………………………………………………………………………………. 15-85
Table 15-24: Full-Time Equivalent Direct, Indirect, and Induced Project Related Employment,
Webequie First Nation, Construction Phase………………………………………………………………….. 15-94
Table 15-25: Project Related Employment Income, Webequie First Nation, Construction Phase…………………. 15-94
Table 15-26: Project Related Employment, Webequie First Nation, Operations phase……………………………… 15-95
Table 15-27: Project Related Employment Income, Webequie First Nation, Operations phase…………………… 15-96
Table 15-28: Full-Time Equivalent Project Related Employment, Other Local Study Area Communities, Construction Phase…………………………………………………………………………………………………. 15-97
Table 15-29: Project Related Employment Income, Other Local Study Area Communities,
Construction Phase…………………………………………………………………………………………………. 15-98
Table 15-30: Project Related Employment, Other Local Study Area Communities, Operations phase………….. 15-98
Table 15-31: Project Related Employment Income, Other Local Study Area Communities,
Operations phase……………………………………………………………………………………………………. 15-99
Table 15-32: Full-Time Equivalent Project Labour Participation, Regional Study Area, Construction………….. 15-101
Table 15-33: Construction Phase Total Jobs in the Regional Study Area by Year – Kenora……………………… 15-103
Table 15-34: Construction Phase Total Jobs in the Regional Study Area by Year – Thunder Bay………………. 15-103
Table 15-35: Construction Phase Total Jobs in the Regional Study Area by Year – Cochrane…………………… 15-103
Table 15-36: Project Related Employment Income, Regional Study Area, Construction Phase…………………. 15-104
Table 15-37: Project Related Employment Income, Kenora, Construction Phase…………………………………… 15-104
Table 15-38: Project Related Employment Income, Thunder Bay, Construction Phase……………………………. 15-104
Table 15-39: Project Related Employment Income, Cochrane, Construction Phase……………………………….. 15-105
Table 15-40: Full-Time Equivalent Project Related Employment, RSA, Operations phase……………………….. 15-105
Table 15-41: Project Related Employment Income, RSA, Operations phase…………………………………………. 15-105
Table 15-42: Project Expenses by Year, Construction Phase……………………………………………………………. 15-107
In Text Tables (Cont’d)
Table 15-43: Total Province of Ontario Effects related to Project Expenditure, Construction Phase……………. 15-107
Table 15-44: Annual Direct, Indirect, and Induced Effects of Project Expenditure, Operations phase –
Province of Ontario……………………………………………………………………………………………….. 15-108
Table 15-45: Direct, Indirect, and Induced Effects of Project Expenditure, Webequie First Nation,
Total Construction Phase………………………………………………………………………………………… 15-108
Table 15-46: Total Effects of Project Expenditure, Webequie First Nation, Construction Phase by Year………. 15-109
Table 15-47: Annual Direct, Indirect, and Induced Effects of Project Expenditure, Webequie First Nation, Operations phase………………………………………………………………………………………………………………………. 15-113
Table 15-48: Direct, Indirect, and Induced Effects of Project Expenditure, Other Local Study Area
Communities, Construction Phase, five to six year Total…………………………………………………. 15-115
Table 15-49: Total Effects of Project Expenditure, Other Local Study Area Communities,
Construction Phase……………………………………………………………………………………………….. 15-115
Table 15-50: Annual Direct, Indirect, and Induced Effects of Project Expenditure, Other Local Study Area Communities, Operations phase………………………………………………………………………………………………………………………. 15-118
Table 15-51: Combined five to six year Construction Phase Economic Effect of Project Expenditure on
the Regional Study Area by Source of Economic Activity……………………………………………….. 15-121
Table 15-52: Construction Phase Total Economic Effect of Project Expenditure on the Regional
Study Area by Year……………………………………………………………………………………………….. 15-121
Table 15-53: Construction Phase Total Economic Effect of Project Expenditure on the Regional
Study Area by Year, Kenora…………………………………………………………………………………….. 15-121
Table 15-54: Construction Phase Total Economic Effect of Project Expenditure on the Regional
Study Area by Year, Thunder Bay…………………………………………………………………………….. 15-122
Table 15-55: Construction Phase Total Economic Effect of Project Expenditure on the Regional
Study Area by Year, Cochrane…………………………………………………………………………………. 15-122
Table 15-56: Operations phase Annual Economic Effects of Project Expenditure on the RSA by
Source of Economic Activity……………………………………………………………………………………. 15-124
Table 15-57: Estimated Occupations of Unemployed, Project Labour Demand, and Estimated
Labour Capture by NOC, Webequie First Nation…………………………………………………………… 15-126
Table 15-58: Full-Time Equivalent Direct Project Related Employment, Webequie First Nation,
Construction Phase……………………………………………………………………………………………….. 15-127
Table 15-59: Estimated Occupations of Unemployed, Project Labour Demand, and Estimated
Labour Capture by NOC, Other Local Study Area…………………………………………………………. 15-129
Table 15-60: Direct Full-Time Equivalent Labour Requirements by Industry, Construction Phase,
Other LSA Communities…………………………………………………………………………………………. 15-130
Table 15-61: Full-Time Equivalent Direct Project Employment, Other Local Study Area,
Construction Phase, Other LSA Communities……………………………………………………………… 15-130
Table 15-62: Estimated Labour Capture by NOC, Thunder Bay, Kenora, and Cochrane,
Construction Phase……………………………………………………………………………………………….. 15-132
Table 15-63: Full-Time Equivalent Direct Project Related Employment, Thunder Bay, Kenora,
Cochrane, Construction Phase…………………………………………………………………………………. 15-133
Table 15-64: Forecasted Direct Project Expenses by Year, Construction Phase……………………………………. 15-136
Table 15-65: Forecasted Direct Project Labour Expenses by Year, Construction Phase………………………….. 15-136
Table 15-66: Estimated Project Operations and Maintenance Expenses……………………………………………… 15-136
In Text Tables (Cont’d)
Table 15-67: Effect of the Project on Provincial Tax Revenue Over a 15-year Time Period
(5 Years of Construction + 10 Years of Operations and Maintenance)……………………………….. 15-137
Table 15-68: Project Contingency Expenses, Construction Phase……………………………………………………… 15-137
Table 15-69: Effect of the Project on Federal Tax Revenue Over a 15-year Time Period
(5 Years of Construction + 10 Years of Operations and Maintenance)……………………………….. 15-138
Table 15-70: Repair Construction Industry Multipliers……………………………………………………………………… 15-138
Table 15-71: Potential Effects, Pathways and Indicators for Regional and Local Economy
Valued Component……………………………………………………………………………………………….. 15-139
Table 15-72: Potential Project Related Interactions with CCP Action Items…………………………………………… 15-145
Table 15-73: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Regional and Local Economy VC……………………………………………………………………………… 15-149
Table 15-74: Criteria for Characterization of Predicted Net Effects on Regional and Local Economy VC……… 15-151
Table 15-75: Summary of Predicted Net Effects on Regional and Local Economy VC…………………………….. 15-160
Table 16-1: Key Regulations, Legislations, Policies Relevant to Non-Traditional Land and Resource Use…….. 16-7
Table 16-2: Non-Traditional Land and Resource Use – Summary of Inputs received during Engagement
and Consultation…………………………………………………………………………………………………….. 16-11
Table 16-3: Non-Traditional Land and Resource Use VCs – Summary of Indigenous Knowledge Shared
with the Project………………………………………………………………………………………………………. 16-13
Table 16-4: Non-Traditional Land and Resource Use VCs – Indicators and Rationale…………………………….. 16-15
Table 16-5: Project Interactions with Land and Resource Use (non-Indigenous) VCs and Potential Effects…. 16-19
Table 16-6: Summary of Methods Data Sources for Non-Traditional Land and Resource Use VCs……………. 16-26
Table 16-7: Webequie Draft CBLUP – New Road Development………………………………………………………… 16-40
Table 16-8: Webequie First Nation Draft CBLUP – Commercial Enterprises…………………………………………. 16-62
Table 16-9: Webequie First Nation Draft CBLUP – New and Existing Commercial Tourism………………………. 16-63
Table 16-10: Webequie First Nation Draft CBLUP – Mineral Exploration and Development………………………… 16-65
Table 16-11: Existing Mining Claims and Tenure in the LSA………………………………………………………………. 16-65
Table 16-12: Existing Aggregate Deposits within the LSA………………………………………………………………….. 16-67
Table 16-13: Webequie First Nation Draft CBLUP – Aggregate Extraction……………………………………………… 16-67
Table 16-14: Webequie First Nation Draft CBLUP – Commercial Timber Harvest…………………………………….. 16-70
Table 16-15: Webequie First Nation Draft CBLUP – Energy Transmissions and Communications Corridors…… 16-72
Table 16-16: Existing Mining, Land Tenure and Aggregate in the RSA………………………………………………….. 16-75
Table 16-17: Proposed and Planned Industrial Developments in the RSA……………………………………………… 16-76
Table 16-18: Status of Energy Resources and Connections of First Nations Communities in the RSA………….. 16-78
Table 16-19: Recreation Activities and The Needs and Barriers for Youth and Women in Webequie
First Nation……………………………………………………………………………………………………………. 16-81
Table 16-20: Webequie First Nation draft CBLUP – Recreational Activities…………………………………………….. 16-83
Table 16-21: Barriers to Recreation Perceived by Youth……………………………………………………………………. 16-86
Table 16-22: Recreation in First Nations Communities in RSA……………………………………………………………. 16-87
Table 16-23: Socio-Economic Survey Responses for Recreation by Weenusk and Marten Falls First Nations 16-88
Table 16-26: Summary of Indigenous Comments on Resources that Support Recreation………………………….. 16-91
Table 16-27: Webequie First Nation Draft CBLUP – Tourism………………………………………………………………. 16-94
Table 16-28: ANSI in the RSA……………………………………………………………………………………………………. 16-100
Table 16-29: Ontario Winter Road Systems and Connected Communities in the Local Study Area……………. 16-105
Table 16-30: Local Study Area Communities Within or Nearby Secondary Watersheds………………………….. 16-107
In Text Tables (Cont’d)
Table 16-31: Ontario Winter Road Systems and Connected Communities in the Regional Study Area………. 16-109
Table 16-32: Summary of Traffic Volume and Collisions in the RSA……………………………………………………. 16-110
Table 16-33: Ontario Airlines with Services to Remote Communities in the RSA……………………………………. 16-111
Table 16-34: First Nations Within or Near Secondary Watersheds in the RSA……………………………………… 16-113
Table 16-35: Potential Effects, Pathways and Indicators for Non-Traditional Land and Resource Use
Valued Component……………………………………………………………………………………………….. 16-116
Table 16-36: WSR Length and Area on Lands………………………………………………………………………………. 16-120
Table 16-37: Summary of Webequie First Nation On-Reserve Land Use Plan – Development Review
and Approval Guidelines…………………………………………………………………………………………. 16-121
Table 16-38: Summary of Conditions for New Road Development and Maintenance, Webequie First Nation
draft CBLUP………………………………………………………………………………………………………… 16-126
Table 16-39: WSR Project Footprint in Draft CBLUP Land Use Zones………………………………………………… 16-128
Table 16-40: First Nations Areas of Interest in Planning within Project Footprint, Local Study and
Regional Study Area………………………………………………………………………………………………. 16-129
Table 16-41: Highlights from First Nations CBLUP Terms of Reference for Transportation Infrastructure…….. 16-129
Table 16-42: Stewardship Highlights of First Nations and Tribal Councils in the RSA……………………………… 16-130
Table 16-43: Existing Mining Claims and Land Tenure in the Project Footprint and LSA………………………….. 16-132
Table 16-44: Number and Area of Existing Aggregate Sources in Project Footprint, LSA and RSA……………. 16-134
Table 16-45: Number and Locations of Camps, Tent Frames and Cabins in the Project Footprint,
LSA and RSA………………………………………………………………………………………………………. 16-137
Table 16-46: List of Navigable Waterbody Crossings for WSR………………………………………………………….. 16-140
Table 16-47: Summary and Conclusion of Potential Effects for the Non-Traditional Land and
Resource Use VCs………………………………………………………………………………………………… 16-154
Table 16-48: Federal and Provincial Policy Tools to Restrict Road Access…………………………………………… 16-155
Table 16-49: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Non-Traditional Land and Resource Use VCs………………………………………………………………. 16-169
Table 16-50: Criteria for Characterization of Predicted Net Effects on Land and Resource Use VC……………. 16-171
Table 16-51: Summary of Predicted Net Effects on Non-Traditional Land and Resource Use VC………………. 16-179
Table 16-52: Scores Assigned for Key Criteria (Categories) of the Predicted Net Effects………………………… 16-180
Table 16-53: Determination of Significance for the Non-Traditional Land and Resource Use VCs……………… 16-182
Table 16-54: Summary of Follow-up and Monitoring……………………………………………………………………….. 16-186
Table 17-1: Key Regulation, Legislation, Policy, and Framework Relevant to Human Health………………………. 17-6
Table 17-2: Human Health VC – Summary of Inputs Received During Engagement and Consultation………….. 17-8
Table 17-3: Human Health VC – Determinants of Health, Indicators, and Rationale……………………………….. 17-15
Table 17-4: Human Health VC – Project Interactions with Determinants of Health…………………………………. 17-20
Table 17-5: Summary of Potential Effects, Pathways and Indicators for Human Health VC………………………. 17-36
Table 17-6: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Human Health VC…………………………………………………………………………………………………… 17-86
Table 17-7: Criteria for Characterization of Predicted Net Effects on Human Health VC………………………….. 17-99
Table 17-8: Definition of Magnitude Ratings for Predicted Net Effects on Human Health VC…………………… 17-101
Table 17-9: Summary of Predicted Net Effects, Significance Evaluation, and Level of Confidence in the Assessment of Effects on Human Health VC 17-111
Table 18-1: Visual Environment VC – Summary of Input Received During Engagement and Consultation…….. 18-5
In Text Tables (Cont’d)
Table 18-2: Visual Environment VC – Summary of Indigenous Knowledge and Land and Resource Use Information……………………………………………………………………………………………………………… 18-6
Table 18-3: Visual Environment VC – Subcomponents, Indicators, and Rationale……………………………………. 18-7
Table 18-4: Project Interactions with Visual Environment VC and Potential Effects………………………………… 18-10
Table 18-5: Results of Visual Assessment of Major Waterbody Crossings…………………………………………… 18-21
Table 18-6: Visibility Parameters and Outcomes……………………………………………………………………………. 18-23
Table 18-7: Summary of Potential Effects, Pathways, and Indicators for Visual Environment VC………………. 18-24
Table 18-8: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Visual Environment VC…………………………………………………………………………………………….. 18-26
Table 18-9: Criteria for Characterization of Predicted Net Effects on Visual Environment VC……………………. 18-27
Table 18-10: Summary of Predicted Net Effects on Visual Environment VC…………………………………………… 18-30
Table 20-1: Key Regulation, Legislation, Policy Relevant to Cultural Heritage and Archaeological Resources… 20-5
Table 20-2: Cultural Heritage and Archaeological Resources – Summary of Inputs Received During
Engagement and Consultation…………………………………………………………………………………….. 20-7
Table 20-3: Cultural Heritage and Archaeological Resources VC – Summary of Indigenous Knowledge and
Land and Resource Use Information…………………………………………………………………………….. 20-9
Table 20-4: Cultural Heritage and Archaeological Resources VC – Subcomponents, Indicators, and
Rationale………………………………………………………………………………………………………………. 20-13
Table 20-5: Project Interactions with Cultural Heritage and Archaeological Resources Valued Component
and Potential Effects……………………………………………………………………………………………….. 20-16
Table 20-6: Summary of Known and Potential Cultural Heritage Landscapes within the Project Study Areas .20-22 Table 20-7: Potential Effects, Pathways and Indicators for Cultural Heritage and Archaeological
Resources VC……………………………………………………………………………………………………….. 20-29
Table 20-8: Summary of Potential Effects, Mitigation Measures and Predicted Net Effects for
Cultural Heritage and Archaeological Resources VC……………………………………………………….. 20-33
Table 23-1: Key Regulation, Legislation and Policy Relevant to the Assessment of Accidents and Malfunctions23-4 Table 23-2: Summary of Accident and Malfunction Input Received During Engagement and Consultation……. 23-6
Table 23-3: Definitions for Categories of Likelihood and Consequence…………………………………………………. 23-9
Table 23-4: Risk Evaluation Matrix……………………………………………………………………………………………….. 23-9
Table 23-5: Potential Accident or Malfunction Scenarios………………………………………………………………….. 23-11
Table 23-6: Accidents and Malfunctions – Potential Interactions with Valued Components………………………. 23-20
Table 23-7: Accident or Malfunction Event Likelihood, Consequence and Risk Evaluation Determination……. 23-33
Table 24-1: Summary of Input Received During Engagement and Consultation………………………………………. 24-6
Table 24-2: Summary of Indigenous Knowledge and Land and Resource Use Information………………………… 24-8
Table 24-3: Summary of Risk Ratings for Climate and Environmental Hazards That May Affect the Project… 24-10
Table 24-4: Past Climate Norms for Stations Nearest to Webequie (ECCC, 2024)…………………………………. 24-19
Table 24-5: Extreme Values at Meteorological Stations Nearest to Webequie (ECCC, 2024)……………………. 24-23
Table 24-6: Hazards/Events, Pathways, and Potential Effects of the Environment on the Project………………. 24-29
Table 24-7: Potential Effects and Key Mitigation Measures for Effects of the Environment on the Project……. 24-30
Table 24-8: Criteria for Characterization of Predicted Net Effects for Effects of the Environment on
the Project…………………………………………………………………………………………………………….. 24-32
Table 24-9: Summary Net Effects Characterization for Effects of the Environment on the Project……………… 24-35
Table 25-1: Summary of Effects and Assessment of Obligations and Commitments………………………………. 25-10
In-Text Photographs
Photograph 4-1: View of Typical Composite Steel-Concrete Bridge………………………………………………………. 4-19
Photograph 4-2: Open Bottom Steel Arch Culvert Under Construction…………………………………………………… 4-20
Photograph 4-3: Completed Open Bottom Steel Arch Culvert………………………………………………………………. 4-20
Photograph 4-4: Typical Corrugated Steel Pipe………………………………………………………………………………… 4-21
Photograph 4-5: Typical Steel Arch Culvert……………………………………………………………………………………… 4-21
Photograph 4-6: Typical Layout of Temporary Construction Camp and Laydown/Storage Area……………………. 4-33
Photograph 4-7: Typical Potable Crushing Plant……………………………………………………………………………….. 4-42
Appendices
A1: Table of Concordance with Tailored Impact Statement Guidelines
A2: Table of Concordance with Provincial Environmental Assessment Terms of Reference B: Qualifications and Roles of the Project Team Members
C-1: Background Studies
C-2: Factors, Disciplines, Criteria, and Indicators
C-3: Multiple Accounts Assessment Datasets
D-1: Preliminary-Engineering-Design-Report Link
D-2: Potential Aggregate Development Sites Report Link E: Mitigation Measures
F: Natural-Environment Existing Conditions Report Link G: Air Quality Impact Assessment Report
H: Greenhouse Gas Emissions Report
I: Climate Change Resilience Review Report
L: Socio-Economic-Existing-Conditions-Report Link J: Noise Vibration Technical Report
K-1: Veg Wetlands Function Effects Modelling
K-2: Veg Invasive Species Clean Equipment Checklist CEP K-3: Veg Conceptual Restoration Plans
K-4: Veg Wetland Function Monitoring Program
L: Socio-Economic-Existing-Conditions-Report Link M: GBA+ WSR Link
N: Community Readiness Plan Link O: Country Foods Assessment Report
P: Human Health Risk Assessment Report Q: Health Impact Assessment Report
R: Visual Impact Assessment Report S: Cultural Heritage Report
T: Stage 1 Report REDACTED
AtkinsRéalis 191 The West Mall Toronto, ON M9C 5L6 Canada 416.252.5315 atkinsrealis.com |
© AtkinsRéalis except where stated otherwise |